UARS Weekly Status Report

18 December 1998




********************************************************************

                UARS WEEKLY STATUS REPORT - 18 DEC 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, collecting solar data on all
available orbital tracking periods and stellar calibration observations,
whenever possible.

***********
SUSIM
***********

SUSIM successfully gathered its normal solar, offset, and occulation
data during this past week without apparent problems.

Reprocessing of all SUSIM experiment days to version 20 continues.

***********
PEM
***********

     PEM is currently conducting tests of the OBC activation.  PEM activation
occurs during daylight only, when there is adequate power generated from 
the UARS solar array.  Currently, the PEM magnetometer and medium energy 
spectrometers (particles below 30 keV) activate correctly under OBC control.
Tests conducted on the high energy particle spectrometers (HEPS -- particles 
greater than 30 keV) have had limited success.  New OBC activation procedure 
for HEPS based on previous tests has been created.  Tests of the new activation
sequence will begin shortly.  Due to testing, HEPS science data between 
December 1 and December 15 should be considered invalid and not used.

***********
HALOE 
***********

HALOE was powered on December 17, 1998.  All engineering parameters are
nominal and science channel exoatmospheric values are within their expected
range.  Science data processed results will be available the beginning of
next week.

HALOE science data version 19 reprocessing is complete.  The data will be
available on the HALOE web site in January after the data validation is
complete.

***********
MLS
***********

The instrument is now off as scheduled.

***********
HRDI
***********

HRDI continues to operate normally, currently running in the 'daytime
only' mode.

Many thanks to all the Goddard folks who helped us during our recent
communications problems.

Since this is likely to be our last status report for 1998, we would like
to wish everyone Merry Christmas and a Happy New Year, and
continued funding in 1999.

***********
WINDII
***********

Version 5 of the WINDII production software is still undergoing
testing, and has not yet been promoted to production; that
should happen early in 1999.  The WINDII Team extends the best 
wishes of the Season, and for the New Year to all members of
the UARS Community.  

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues  
with no problems.  The MPG continues to assist the Project 
Scientist with the scheduling of instrument operations. 
  
***********
CDHF
***********

The UK Meteorological Office has resumed sending UKMO data to the CDHF after
computing problems were resolved.  No backlog exists.
                          
The CDHF processed current day data through level 3 for all active
   instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.
              9 days HAL (4.80) PROD (L2-L3) (89R-89C=0L)
             62 days HAL (4.80) PROD (L3)    (1874R-1538C=336L)
             41 days SOL (4.62) PROD (L2-L3) (2313R-2239C=74L)
             18 days SUS (7.00) PROD (L1)    (43R-43C=0L)
             63 days SUS (7.00) PROD (L3)    (2540R-886C-4F=1650L)
              3 days CLA (7.00) ENG  (L1-L3) (24R-24C=0L)
                    
The CDHF has started the installation of IDL software to version 5.1. 

The CDHF met with UCSS developers to discuss and try to determine why the
wallclock times of the SOLSTICE V4.60 production reprocessing is steadily 
increasing with the mission day number.  The CDHF demonstrated the UCSS
Scheduler methodology concerning the SOLSTICE scheduling and setup.  

CDHF pending software upgrades: IDL 5.1, OpenIngres, UCSS 10.1, MSS 4.1,
NRT 2.5, UOAS 5.4  
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 05 December 1998 (Orbit 39522, GMT Day 345) through 11 
December 1998 (Orbit 39627, GMT Day 345).


SPACECRAFT OPERATION

The observatory is now in Reverse Flight (Northern Hemisphere viewing) and 
is performing nominally under two-battery operations.  The instrument 
operational changes were:

                    INSTRUMENT OPERATIONAL CHANGES

             Instrument     Time          Orbit     Comment
               WINDII     342/0047       39568      On
               HALOE      343/2307       39597      Off

The beta angle ranged between 37.0 degrees to 9.0 degrees for this report 
period. The beta angle is now decreasing toward a minimum angle of -1.0 
degrees on 13 December 1998 (DOY 347).

PEM successfully tested its latest revision, a 37 command HEPS 
microprocessor RAM patch with RTS one-second delay timing every four 
commands.  The ability to do extra long RTS loads will reduce the overhead 
in the existing RTS's and allow workarounds.  The test results are being 
evaluated.

Spacecraft battery 1, 2, and 3 performance monitoring continues.  Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 1.0 to 1.4 degrees C.  Additional battery performance data 
for each battery on 04 December 1998 and 11 December 1998 are provided in 
Appendix D.

The clock error ranged from 9.9 to -10.5 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

%     ALERTS        =     00
%     OUT-OF-LIMITS =     02

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     02
%     HALOE   02
%     PEM     02
%     WINDII  01

UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     02

One (1) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
     Transponder A:  98/286  -  2287.496936
     Transponder B:  98/300  -  2287.498964


GROUND SYSTEM OPERATION

One (1) operational support problems occurred this period.  Anomaly Reports 
are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/337 show the observatory data loss to be 
21 hours, 40 minutes, 14.260 seconds (an increase of 7.488 seconds since 
last report period).  This is a 0.0342 percent data loss which equals a 
99.9658 percent data capture for the mission.

The increase of 7.488 seconds occurred over five (5) days:

7 0.224 seconds on Day 338 due to data hit;
7 1.536 seconds on Day 339 due to hit in data (IP);
7 1.696 seconds on Day 341 due to data hit and hit in data (IP);
7 2.272 seconds on Day 342 due to hit in data (IP); and
7 1.760 seconds on Day 344 due to hit in data (IP).

Two (2) new versions of Relative Time Sequence 32 (RTS 32) were generated 
this week to refine the PMON controlled operation of HEPS1 portion of the 
PEM instrument.

Flight Dynamics Facility (FDF) had to re-generate this week long term (8-
week) planning aids due to a last minute change by FOT in the planned 
maneuver time for the upcoming UARS Roll Offset maneuver.  The FOT time 
change delayed planning aid delivery that subsequently resulted in the FOT 
being behind schedule in much of their long-term planning tasks (i.e. TDRS 
scheduling, SSPP Sunplan generation, etc).


OTHER SIGNIFICANT EVENTS

UARS SATELLITE OPERATIONS

Preparation of 0.5 degrees (colds side down) roll procedure to be executed 
in December 1998 and January 1999 was completed and tested using the UARS 
Test and Training Simulator (UTTS) on 08 December 1998.  The UTTS testing 
proceeded without error.  The procedure and plan are now ready to be used 
when scheduled on 351/14:55 UTC (17 December 1998).

Development of the procedure for the clock change to include the 01 January 
1999 leap second adjustment continues.

FOT plans to begin testing of the Orbit Adjust Maneuver on the UTTS 
(simulator) in December 1998.  Two versions will be tested; one with B/D 
thrusters and; one with A/C thrusters.  The next orbit adjust will not be 
needed until late 2000 (or later if the altitude limits are lowered).

Flight Operations and SOLSTICE have completed and verified the plan for 
SOLSTICE Day-Only Operation.  SOLSTICE will select a date for transition to 
day-only operation.

Investigating the feasibility of a new PMON action to change battery V/T 
curves based on loading to mitigate battery risks in sun pointing safehold.


YEAR 2000 OPERABILITY SUPPORT

UARS Test and Training Simulator (UTTS) - No change.

User Planning System (UPS) - No change.

Multi Satellite Operations Control Center (MSOCC) - No change.

Command Management System (CMS) - A set of long-term PSAT and S/C Orbital 
Events files for Y2K testing which have consistent orbit numbers has been 
received.  All previously delivered sets of PL and OL files for the 1999-
to-2000 century crossover had orbit numbers which did not line up with the 
other files, making it impossible to process them on the CMS.  Now that the 
FOT has a correct set of these two files, they can proceed with Y2K testing 
and hopefully finish up all of the test functions related to these 
products.

Flight Dynamics Facility (FDF) - see CMS paragraph.


UARS PROPULSION MODULE B/D THRUSTER LINE FILL

Planning continues for the simulator testing.


UARS RE-ENGINEERING - TELEMETRY PROCESSING

Testing of the Trending System v.1.1 release (CM-0009) continued.


MEETINGS

None


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is scheduled for scheduled for 13 
December 1998.

The United States Naval Observatory (USNO) issued  a Time Service 
announcement advising that the International Earth Rotation Service (IERS) 
will retard UTC time by 1.0 second at the end of December 1998. This means 
the addition of one leap second as the last second of 1998.

The next annular solar eclipse will occur on 16 February 1999 over the 
Indian Ocean, Australia and the South Pacific Ocean.


PERSONNEL CHANGES

none


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports




                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 11 December 1998

ORBIT       AOS        NO.      SUBSYS         REASON
-----       ---        ---     ------         -------  
39524     339/0228    98-486     OBC      Clk Adj fr 0.00 to 20.6 msec/day
39532     339/1455    98-487     HALOE    Update SR & SS due to CS 4 error
39548     340/1608    98-488     OBC      Clk Adj fr 20.6 to 0.00 msec/day     
39568     342/0047    98-489     WINDII   Power ON
39577     342/1605    98-490     PEM      PEM RTS loads
39595     343/1945    98-491     PEM      PEM RTS loads
39597     343/2307    98-492     HALOE    Power OFF

_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 11 December 1998

MNEMONIC         STATE      DESCRIPTION                    ORBITS
---------        -----      ------------                   ------
HACS4           Y-HI     Control status word 4      39532,33
HRPSEQBIMON     Y-HI     PSE QB Current Monitor     39588


The following ALERT occurrences were detected:

MNEMONIC                   DESCRIPTION                      ORBITS
---------                 ------------                      ------
                   None this report period



_______________________________________________________________

                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 11 December 1998


                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                 CLOCK RATE CHANGE
     -----              ----                 -----------------
     39524     339/02:28 (05 Dec 98)     from 00.0 to 20.6 msec/day
     39548     340/16:08 (06 Dec 98)     from 20.6 to 00.0 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 11 December 1998


     04 Dec 1998 - GMT Day 338 Beta = 37.0 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1   +84.0/+56.0  -3.05/-4.62   +0.0/ +0.0    16.8    0.000    0.0
2   +28.0/-22.4  +5.47/+4.51  +29.6/-15.2    25.8    1.027   21.0
3   +56.0/-5.6   +4.51/+2.92  +28.8/-15.2    25.8    1.026   20.7


     11 Dec 1998 - GMT Day 345 Beta = 9.0 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1   +78.4/+56.0  -3.68/-4.94   +0.0/ +0.0    16.8    0.000    0.0
2   +44.8/-5.6   +5.47/+4.19  +31.6/-14.4    25.4    1.020   21.5
3  +134.4/0.0    +4.19/+2.92  +30.4/-14.4    25.4    1.020   21.0


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes (V/T 5)



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 11 December 1998


                      NEW ANOMALY REPORTS GENERATED
  AR NO.   SUBSYS   ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------   ------   -----      ----       ---      -----------------
98-121     FOT     39531     339/1243     N/A      Halo CS4 error
98-117     FOT     39534     339/1812     14170    Generic Late Acquisition


                   ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO.   SUBSYS   ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------   ------  -----       ----       ---      -----------------
98-120      FOT     39521     338/21:15           OP ERROR INST LD
98-121      FOT     39532     339/14:55           HALOE CS4 ERROR


                ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS   ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  -------  ------   -----      ----       ---      -----------------
                    None this report period


                         OPEN ANOMALY REPORTS
  AR NO.   SUBSYS       ORBIT      TIME       TTR    PROBLEM/DATA LOSS
  ------   ------       -----      ----       ---    -----------------
98-117     FOT     DEC 98     See List     14170     GENERIC LATE ACQ


	 	SEVNTFW50