******************************************************************** UARS WEEKLY STATUS REPORT - 10 DEC 1999 ******************************************************************** *********** SOLSTICE *********** Data gaps due to the current tape recorder operations cause us to only loose 20-30% of our planned experiments. Otherwise, SOLSTICE continues to operate normally, collecting solar data on all available orbital tracking periods and stellar calibration observations, whenever possible. *********** SUSIM *********** SUSIM gathered a minimum set of daily solar scans this past week. Because many of these occurred during telemetry outages, all of the data was not retrieved. We would be able to schedule SUSIM's solar scans during TDRS contacts if these were known sufficiently in advance. *********** ACRIM *********** Nothing received. *********** PEM *********** Nothing received. *********** HALOE *********** Nothing received. *********** MLS *********** Nothing received. *********** HRDI *********** Nothing received. *********** WINDII *********** WINDII is scheduled for observations December 15 - 23, 1999. It will be operated in PMC observing mode for southern high latitudes. *********** MPG *********** Routine processing of instrument Daily Activity Plans continues with no problems. The MPG continues to assist the Project Scientist with the scheduling of instrument operations. The MPG is assisting the FOT with their analysis of the tape recorder (NBTR B) anomaly. *********** CDHF *********** The CDHF processed current day data through level 3 for all active instruments. Additionally, CDHF personnel reprocessed: (R)= Requested (C) = Complete, (F)= Failed (L) = Days remaining to reprocess. 17 days CLA (7.0) PROD (L1-L3) (476R-435C-21F=20L) 24 days GPI (4.05) PROD (CLAES L3B) (372R-356C-3F=13L) 42 days WIN (5.11A) PROD (L1-L3) (520R-102C-5F=413L) DAAC DATA: -DAAC data created in the month of September 1999 has been loaded into the DAAC Transfer Tables for HALOE, NMC, PEM, and UKMO. UARS CDHF REHOST: -Reprocessing HALOE test V4.82 on the Rehost System. -Successfully tested SUSIM V7.1 on the Rehost System. Output files have been moved to an area for SUSIM validation. -Planning and preparing to test SOLSTICE V4.62 on the Rehost System. -Migration for all data levels continued. *********** FOT *********** REPORTING PERIOD This report covers 27 November, 1999 (Orbit 44870, GMT Day 331) through 03 December 1999 (Orbit 44974, GMT Day 337). SPACECRAFT OPERATION The observatory is now in Reverse Flight (Northern Hemisphere viewing) and is performing nominally under two-battery operations. The instrument operational changes were: INSTRUMENT OPERATIONAL CHANGES Instrument Time Orbit Comment PEM 332/2314 44899 AXIS Off The beta angle ranged between the angles of 50.3 degrees to 21.4 degrees for this report period. The beta angle is now decreasing toward a minimum angle of -2.0 degrees on 08 December 1999 (DOY 342). Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 remains OFF the charge relay. Battery 2 and Battery 3 are currently maintaining greater than 23.8 V end-of-night (EON) load bus voltage. Battery temperatures are stable with a temperature delta between Battery 2 and Battery 3 of 1.0 to 1.3 degrees C. Additional battery performance data for each battery on 26 November 1999 and 03 December 1999 are provided in Appendix D. The clock error ranged from -13.3 to 11.9 msec during this report period. Clock rate adjustments are listed in Appendix C. All instrument and subsystem engineers were advised on the initial excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for this report. A summary is listed below and the details of ALERT and Out-Of-Limits occurrences are listed in Appendix B. % ALERTS = 00 % OUT-OF-LIMITS = 01 The following real-time command sheets were executed for the listed operational element(s) during this report period (see Appendix A). % FOT = 06 % SUSIM = 01 % PEM = 01 UARS Anomaly Reports initiated during this report period are listed in Appendix E and summarized below. % FOT = 06 One (1) Anomaly Reports remained OPEN at the end of this report period (see Appendix E). TRANSPONDER FREQUENCIES: % Transponder A: 99/320 - 2287.496800 % Transponder B: 99/334 - 2287.499196 GROUND SYSTEM OPERATION Six (6) operational support problems occurred this period. Anomaly Reports are included in Appendix E. The data loss calculations supplied by Data Capture Facility (DCF) from mission start through UTC Day 99/336 show the observatory data loss to be 226 hours, 31 minutes, 08.953 seconds (an increase of 41 hours 11 minutes 22.080 seconds since the last report period). This is a 0.3154 percent data loss which equals a 99.6846 percent data capture for the mission. The increase of 41 hours 11 minutes 22.080 seconds occurred over seven (7) days: - 06 hours 24 minutes 55.936 seconds on Day 330 due to a S/C TR problem. - 06 hours 03 minutes 10.016 seconds on Day 331 due to a S/C TR problem. - 05 hours 38 minutes 44.608 seconds on Day 332 due to a S/C TR problem. - 05 hours 58 minutes 02.944 seconds on Day 333 due to a S/C TR problem. - 05 hours 50 minutes 44.896 seconds on Day 334 due to a S/C TR problem. - 05 hours 43 minutes 52.672 seconds on Day 335 due to a S/C TR problem. - 05 hours 31 minutes 51.008 seconds on Day 336 due to a S/C TR problem. OTHER SIGNIFICANT EVENTS UARS SATELLITE OPERATIONS The FOT implemented test 9; Power NBTR A, record, dump and process. This test was done on Tuesday, November 30, 1999. It was powered up and left in the standby mode for 1/2 an orbit to verify thermal stability or any other anomalous trend. It was then spooled from beginning of tape to end of tape twice and then placed into 8-mux record. The recorder was allowed to record in its entirety and then played back. During the playback, White Sands reported no lock on data and TPF reported no valid blocks as well. This test was repeated in the 4-mux mode on Wednesday, December 1, 1999. White Sands and TPF reported no frame synch and no valid blocks respectively. The remaining tests are of a more critical nature and will be determined at a later time whether or not to implement them. YEAR 2000 OPERABILITY SUPPORT All areas identified to or by the Flight Operations Team for Y2K testing have been completed. There are no other areas identified at this time that have not been Y2K certified. MEETINGS Wednesday, December 1, 1999 (DOY 335) - A meeting was held to discuss the status of NBTR A. The key points are as follows: - The need for a plan to operate NBTR B in the best possible manner to maximize science data. - Due to the diversity of the science missions with respect to their ideal recording times, an order of importance should be identified. HALOE was identified to have the highest priority with the use of the PASS 2 side of NBTR B. - Consider the possibility of using the recorder for special requests only. - Can PASS 2 operations and realtime coverage be coordinated to maximize science data coverage? This question was preliminarily answered with only a 10% increase in data capture by using the recorder. - Other topics were discussed such as power concerns, three TDRSS usage, anomaly investigation, releasing TPF acceptance restrictions and etc... Thursday, December 2, 1999 (DOY 336) - The FOT attended a meeting to answer questions regarding a new plotting system for UARS. Currently Health and Safety telemetry processing takes hours to process just a few orbits of data. A new system being reviewed is a Sun Workstation based system that would have a window environment and produce plots in seconds or minutes. The FOT is involved with providing additional samples and information to facilitate this action. FUTURE SIGNIFICANT EVENTS No specific date was agreed upon for UARS Safehold configuration discussions. Instead, the Supporting Engineers involved will be contacted every two weeks to determine if either the Flight Operations Team or Supporting Engineers have any new developments that should be discussed in a group. It is expected that one more meeting will be held before Y2k as an update to UARS safehold expectations for the new century. UARS has tested and prepared for the Year 2000 event. Special considerations have been made in preparation for a non nominal 1999 to 2000 transition. The next UARS Yaw slew is scheduled for December 8, 1999. This maneuver will be a Reverse to Forward Flight maneuver(Southern Hemisphere viewing). Attachments: Appendix A, Real-time Commands Sheets Appendix B, Out-Of-Limits & ALERT Occurrences Appendix C, Clock & Solar Array Rate Corrections Appendix D, UARS Battery Performance Data Appendix E, UARS Anomaly Reports APPENDIX A REAL-TIME COMMAND SHEETS Week ending 03 December 1999 ORBIT AOS NO. SUBSYS REASON ----- --- --- ------ ------- 44888 332/0519 99-401 OBC Clk Adj fr 20.6 to 0.00 msec/day 44899 332/2314 99-402 PEM AXIS Power OFF 44925 334/1547 99-403 NBTR NBTR-A TEST 44928 334/2135 99-404 CDH CDH Config. CMDS 44929 334/2247 99-405 OBC Clk Adj 0.00 to 20.6 msec/day 44943 335/2139 99-405 NBTR NBTR-B Power Off 44951 336/1048 99-407 OBC Clk Adj 20.6 to 0.00 msec/day 44955 336/1553 99-408 SUSIM Exception Clear _________________________________________________________________________ APPENDIX B OUT-OF-LIMITS & ALERTS OCCURRENCES Week ending 03 December 1999 The following Out-Of-Limits occurrences were detected: MNEMONIC STATE DESCRIPTION ORBITS --------- ----- ------------ ------ HRPTSPBIMON Y-HI PTS Pulse Bus Current Mon 44918-74 The following ALERT occurrences were detected: MNEMONIC DESCRIPTION ORBITS --------- ------------ ------ No Alerts to report this report period. ______________________________________________________________ APPENDIX C CLOCK & SOLAR ARRAY RATE CORRECTIONS Week ending 03 December 1999 CLOCK DRIFT RATE ADJUSTMENTS ORBIT TIME CLOCK RATE CHANGE ----- ---- ----------------- 44888 332/05:28 (28 Nov 99) from 0.00 to 20.6 msec/day 44929 334/22:55 (30 Nov 99) from 20.6 to 0.00 msec/day 44951 336/10:53 (02 Dec 99) from 0.00 to 20.6 msec/day ______________________________________________________________ APPENDIX D UARS BATTERY PERFORMANCE DATA Week ending 03 December 1999 26 Nov 1999 - GMT Day 330 Beta = 50.3 deg, SA Pos = 269 deg DIFF V (mV) TEMP (C) CURR (amp) EON V AVE C/D AVE BAT MAX/MIN MAX/MIN MAX/MIN MIN RATIO DOD(%) --- ---------- ------- --------- ----- ------- ------ 1 -56.0/-78.4 -3.68/-4.94 +0.0/+0.0 16.2 0.000 0.0 2 +84.0/+0.0 +5.47/+4.19 +28.4/-16.0 25.3 1.030 19.5 3 +22.4/-22.4 +4.51/+2.92 +27.2/-15.2 25.1 1.027 19.1 03 Dec 1999 - GMT Day 337 Beta = 21.4 deg, SA Pos = 269 deg DIFF V (mV) TEMP (C) CURR (amp) EON V AVE C/D AVE BAT MAX/MIN MAX/MIN MAX/MIN MIN RATIO DOD(%) --- ---------- ------- ---------- ---- ------ ------ 1 -50.4/-72.8 -3.05/-4.62 +0.0/+0.0 16.2 0.000 0.0 2 +56.0/-5.6 +6.44/+5.15 +31.6/-15.2 24.8 1.037 20.0 3 +33.6/-33.6 +5.15/+3.87 +31.2/-16.0 24.5 1.035 19.7 V/T LEVEL CHANGES ORB# TIME LVL FR-TO ----- --- --------- no changes V/T 5 APPENDIX E UARS ANOMALY REPORTS Week ending 03 December 1999 NEW ANOMALY REPORTS GENERATED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 99-081 FOT 44871 331/0302 14170 Generic Late Acquisition 99-081 FOT 44885 332/0058 14170 Generic Late Acquisition 99-081 FOT 44900 333/0100 14170 Generic Late Acquisition 99-081 FOT 44906 333/1040 14170 Generic Late Acquisition 99-087 FOT 44911 333/1804 21634 AP-8 NIU Problem 99-088 FOT 44936 335/0940 N/A TAC-4 Crashed ANOMALY CLOSURE INFORMATION RECEIVED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 99-071 FOT 44398 299/1212 21512 TPF Not Receiving 512 PB 99-081 FOT November 14170 Generic Late Acquisition 99-087 FOT 44911 333/1804 21634 AP-8 NIU Problem 99-088 FOT 44936 335/0940 N/A TAC-4 Crashed ANOMALY INVESTIGATION REPORTS GENERATED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- No new reports generated OPEN ANOMALY REPORTS AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 99-064 FOT 44135 10/8-9/99 N/A HRDI Cal Lamp Errors SEVNTFW99/49