UARS Weekly Status Report

07 December 2001




********************************************************************

                UARS WEEKLY STATUS REPORT - 07 Dec 2001

********************************************************************

Please send future UARS Weekly Status Report submissions to
   UMPGAL::STAT  or  "stat@umpgal.gsfc.nasa.gov"

***********
SOLSTICE
***********

SOLSTICE continues normal operations, taking solar data on all available
orbital tracking periods and stellar calibration observations whenever
possible. We continue to gather enough data to meet the SOLSTICE science
objectives during this period of reduced tape recorder operations.

***********
SUSIM
***********

SUSIM completed daily mid resolution and MgII solar scans during
periods of predicted UARS telemetry.

We are awaiting the delivery of attitude and orbit files so that
we can process SUSIM data since Nov. 17.

***********
ACRIM
***********

Nothing received.

***********
PEM
***********

***** ALL PEM COMMUNICATION SHOULD NOW BE THROUGH THE PEM2K:: NODE *****

     PEM began daylight operations on 2001333 and the PEM/AXIS-1 was also 
activated on 2001333.

     Verification of PACOR-A files is complete and verified.  Binaries were 
not the same from PACOR-A as from CDHF so these data files were processed 
to science data and the science data was compared.  As suspected, the version 
number field contained a different value which caused the binaries to differ.
PEM does not use Quicklook data; however, PEM has used NRT data from
the CDHF to verify instrument operations in the past.  PEM assumes that NRT
data will no longer be available...(Correct?)

     PEM performed tests of NMC data files from both the CDHF and NOAA.  NMC 
data files from both systems were captured and read.  PEM is now capturing
NMC data directly from the NOAA web site.  An automated-cron unix c-shell 
script is available from PEM if it can be of use to others.  For a copy, 
contact: rudy@pemrac.space.swri.edu or PEM2K::RUDY.

     An outstanding question from PEM is the UARS Orbit and Attitude.  Some 
discussion has taken place about the UARS ORBIT data but there has been no 
indication on how UARS attitude data is being distributed to the 
experimenters.  In addition, PEM uses UARS OA Services-UOAS extensively and 
that software has not been made available.  It is unclear as to how attitude 
information is to be determined.


*Beginning of power orbit day (PEM activation): array current >5 amps, array 
     voltage >53.5 volts, and battery current >2.0 amps.  
 End of power orbit day (PEM deactivation): time in power orbit day >4 minutes,
     array current <9 amps, and battery currents <0.2 amps.
 Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

HRDI continues to function normally, making wind measurements during
the sunlit parts of orbits nearly every day, and measuring nighttime winds
when power is available.

***********
WINDII
***********

Nothing received.

***********
MPG
***********

The MPG continues to serve as the point-of-contact
for UARS instrument operations to support re-engineering
of the UARS Mission Operations Concept to develop 
capabilities for the Science Traceability Mission.

Daily processing of instrument Daily Activity Plans 
continues with no problems.  

***********
CDHF
***********

Nothing received.
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 24 November 2001 (Orbit 55787, GMT Day 328) through 
30 November 2001 (Orbit 55891, GMT Day 334).

SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) 
and is performing nominally under two-battery operations.  The 
instrument operational changes were:


INSTRUMENT OPERATIONAL CHANGES


	Instrument	Time	Orbit	Comment
	HRDI	328/1142	55794	TO LOW POWER=09
	SUSIM	3239/2259	55816	Power OFF=09
	SUSIM	332/1445	55856	Power ON (PART-1)=09
	PEM	333/1124	55869	Power ON DAY ONLY=09
	AXIS-1	333/1304	55870	Power ON (7 WATTS)=09
	SUSIM	333/1444	55871	Power ON COMPLETED=09


A Reverse-to-Forward Yaw Around maneuver (number 104) was successfully 
executed in Orbit 55375 beginning 330/14:04:41 and completing at 
330/14:41:51 on 26 November 2001.  The SOLSTICE instrument was in day 
only and all other instruments were in their off or standby mode 
(including HRDI and PEM).  Due to the SA position at 269 degrees, the 
effective night length of the spacecraft after the maneuver was 
approximately 57.1 minutes.  Post maneuver analysis of data indicate 
that during the Yaw Around, the end-of-night load bus voltage was 23.8 
volts and the average depths of discharge (DODs) on Batteries 2 and 3 
were approximately 20.4 and 20.2 percent respectively.  The next 
(reverse-to-forward) YAW is scheduled for 25 December 2001 (DOY 359).

The beta angle ranged between the angles of 10.3 degrees to 12.6 degrees 
for this report period.  The beta angle is now increasing towards a 
maximum angle of 34 degrees on 11 December 2001 (DOY 345).

Spacecraft battery 1, 2, and 3 performance monitoring continues.  
Battery 1 remains OFF the charge relay.  Battery 2 and Battery 3 are 
currently maintaining greater than 23.8 V end-of-night (EON) load bus 
voltage.  Battery temperatures are stable with a temperature delta 
between Battery 2 and Battery 3 of 1.3 to 1.9 degrees C.  Additional 
battery performance data for each battery on 23 November 2001 and 30 
November 2001 are provided in Appendix D.

The clock error ranged from -10.7 to 11.8 msec during this report 
period.  Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and 
Out-Of-Limits occurrences are listed in Appendix B.

	OUT-OF-LIMITS	=3D	00
	ALERTS	=3D	00

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A).

	FOT	=3D	8
	HRDI	=3D	1
	SUSIM	=3D	3
	PEM	=3D	1
	AXIS-1	=3D	1


UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

	None this report period.

Zero (0) Anomaly Report remained OPEN at the end of this report period 
(see Appendix E).

TRANSPONDER FREQUENCIES:
* Transponder A:  00/316  - 2287.496493
* Transponder B:  01/286  - 2287.498613

GROUND SYSTEM OPERATION


Zero (0) operational support problems occurred this period.   Anomaly 
Reports are included in Appendix E.

The data loss calculations are no longer being supplied by Data Capture 
Facility (DCF). This service should resume soon.


OTHER SIGNIFICANT EVENTS


UARS SATELLITE OPERATIONS


The Raytheon development team for the Eclipse system presented the 
System Design Review (SDR) this week in Landover, MD.  The meeting went 
very well and the smoothness of this review showed the progress being 
made by all parties involved.  The Eclipse team is scheduled to supply 
the first release of the system in January, which will begin the testing 
processing.


The FOT held the Operational Readiness Review (ORR) for the TAC 
replacement system this week.  The ORR was held with a lien on the two 
outstanding DRs, which should be fixed soon.  It was decided after this 
presentation that the TACs would be used for operations during the day 
shift timeframe for approximately the next two weeks before being 
released to operations full time.



MEETINGS

The FOT attended a UARS Eclipse Weekly on Monday, November 26, 2001.
The FOT attended a UARS Eclipse SDR on Wednesday, November 28, 2001.
The FOT attended a UARS Eclipse-FDF Meeting on Thursday, November 29, 
2001.
The FOT attended a UARS Eclipse-TAC RS Meeting on Thursday, November 29, 
2001.
The FOT attended a UARS TAC-RS ORR on Thursday, November 29, 2001.

FUTURE SIGNIFICANT EVENTS


The next UARS Yaw slew is scheduled for 25 December 2001 (DOY 330).  
This maneuver will be a Forward to Reverse Flight maneuver (Northern 
Hemisphere viewing).


Attachments:	Appendix A,	Real-time Commands Sheets
	Appendix B,	Out-Of-Limits & ALERT Occurrences
	Appendix C,	Clock & Solar Array Rate Corrections
	Appendix D,	UARS Battery Performance Data
	Appendix E,	UARS Anomaly Reports

APPENDIX A
REAL-TIME COMMAND SHEETS
Week ending 30 November 2001

ORBIT    	AOS     	NO.	SUBSYS   REASON
-----	        ---     	---	------	 ------
55794		328/1142	01-690	HRDI	 TO LOW POWER
55797		328/1640	01-691	OBC/CLK	 Clk Adj -20.6 to 0.00 msec/day
55816		329/2259	01-692	SOLSTICE TO DAY-ONLY MODE
55816		3239/2259	01-693	SUSIM	 Power OFF
55825		330/1321	01-694	MACS	 YAW SCRIPT (MONYAW)
55825		330/1321	01-695	TAM	 OUT OF UPDATE MODE
55826		330/1446	01-694	MACS	 MACS SFHLD TO FWD DIR.
55826		330/1446	01/696	TAM	 ALIGNMENT/TO UPDATE MODE
55854		332/1222	01-698	NBTR	 PBK & RTS-58
55856		332/1445	01-699	SUSIM	 Power ON (PART-1)
55869		333/1124	01-700	PEM	 Power ON DAY ONLY
55870		333/1304	01-701	AXIS-1	 Power ON (7 WATTS)
55871		333/1444	01-699	SUSIM	 Power ON COMPLETED
55871		333/1444	01-702	XMTR	 XMTR-A ON (for OMNI pass)
55871		333/1602	01-702	XMTR	 XMTR-A OFF / TEST CMDS


APPENDIX B
OUT-OF-LIMITS & ALERTS OCCURRENCES
Week ending 30 November 2001

The following Out-Of-Limits occurrences were detected:

MNEMONIC	STATE	DESCRIPTION	ORBITS
--------	-----	-----------	------
-None this report period.


The following ALERT occurrences were detected:

MNEMONIC	DESCRIPTION	ORBITS
--------	-----------	------
-None this report period.

_________________________________________________________________________

APPENDIX C
CLOCK & SOLAR ARRAY RATE CORRECTIONS
Week ending 30 November 2001

CLOCK DRIFT RATE ADJUSTMENTS

ORBIT	TIME	CLOCK RATE CHANGE
-----	-----	-----------------
55797	328/1658	Clk Adj -20.6 to 0.00 msec/day



APPENDIX D
UARS BATTERY PERFORMANCE DATA
Week ending 30 November 2001


	23 November 2001 - GMT Day 327 Beta =3D 13.9 deg, SA Pos =3D 269 deg

	DIFF V (mV)     TEMP (C)        CURR (amp)	EON V	AVE C/D	AVE 
BAT	MAX/MIN  	MAX/MIN		MAX/MIN 	MIN	RATIO	DOD(%)
---	-------	        --------        ----------	-----	-------	------
1	+728.0/+728.0	-3.77/-4.69	 +0.0/ -0.0	10.7	0.000	 0.0
2	 +00.0/ -33.6	+4.48/+4.17	+28.8/-13.6	26.2	1.030	19.1
3	 +22.4/ -22.4	+3.17/+2.20	+28.0/-13.6	26.2	1.030	18.6


	30 November 2001 - GMT Day 334 Beta =3D 12.6 deg, SA Pos =3D 269 deg

	DIFF V (mV)	TEMP (C)	CURR (amp)	EON V	AVE C/D AVE
BAT	MAX/MIN 	MAX/MIN		MAX/MIN	        MIN	RATIO	DOD(%)
---	-------	----------		----------	-----	-------	------
1	+728.0/+728.0	-4.08/-4.99	 +0.0/ -0.0	10.7	0.000	 0.0
2	 +00.0/ -33.6	+4.48/+3.17	+29.6/-13.2	26.4	1.030	19.5
3	 +22.4/ -22.4	+3.17/+2.20	+28.4/-13.2	26.4	1.020	19.0


	V/T LEVEL CHANGES
ORB#	TIME	LVL FR-TO
-----	----	---------
-no changes	V/T 5








APPENDIX E
UARS ANOMALY REPORTS
Week ending 30 November 2001

NEW ANOMALY REPORTS GENERATED
AR NO.	SUBSYS	ORBIT	TIME	TTR	PROBLEM/DATA LOSS
------	------	-----	----	---	-----------------
-None this report period.

	ANOMALY CLOSURE INFORMATION RECEIVED
AR NO.	SUBSYS	ORBIT	TIME	TTR	PROBLEM/DATA LOSS
------	------	-----	----	---	-----------------
01-69	FOT	see list	Nov 01	14170	Generic Late Acquisition

	 ANOMALY INVESTIGATION REPORTS GENERATED
AR NO.	SUBSYS	ORBIT	TIME	TTR	PROBLEM/DATA LOSS
------	------	-----	----	---	-----------------
-None this report period.

OPEN ANOMALY REPORTS
AR NO.	SUBSYS	ORBIT	TIME	TTR	PROBLEM/DATA LOSS
------	------	-----	----	---	-----------------
-None this report period.



		SEVNTFW01/48