UARS Weekly Status Report

27 November 1998





********************************************************************

                UARS WEEKLY STATUS REPORT - 27 NOV 1998

********************************************************************

***********
SOLSTICE
***********

NOTHING RECEIVED.

***********
SUSIM
***********

NOTHING RECEIVD.

***********
PEM
***********

NOTHING RECEIVED.

***********
HALOE 
***********

NOTHING RECEIVED.

***********
MLS
***********

NOTHING RECEIVED.

***********
HRDI
***********

NOTHING RECEIVED.

***********
WINDII
***********

WINDII WEEKLY REPORT FOR THE WEEK ENDING November 27, 1998

WINDII is preparing to include PMC observations during its
southward looking yaw period. This requires a 0.5 degree
roll-down because of the higher orbit altitude in the
southern hemisphere. We appreciate the support for that.


***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues  
with no problems.  The MPG continues to assist the Project 
Scientist with the scheduling of instrument operations. 


***********
CDHF
***********

The CDHF notified all PI representatives regarding unrecoverable data gaps
for UARS DAYS 2624 and 2629 due to problems encountered at POCC.

The CDHF completed several Y2K time shift tests on a subset of the UARS
VMS cluster on November 24th. The system returned to current day without
incident. Mutinet problems were expected and were fixed.  

The CDHF processed current day data through level 3 for all active
   instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.
              1 day  HAL (4.80) PROD (L1)    (1875R-1875C=0L)
             30 days HAL (4.80) PROD (L2-L3) (62R-62C=0L)
             80 days HAL (4.80) PROD (L3)    (1874R-1429C=445L)
             47 days SOL (4.62) PROD (L2-L3) (2313R-2111C=202L)
            103 days SUS (7.00) PROD (L1)    (2370R-507C=1863L)
              3 days CLA (7.00) ENG  (L1-L3) (24R-15C=9L)
              1 day  SEN (5.00) PROD         (1R-1C=0L)
 
The CDHF installed the Y2K ECO patch (Number VAXY2K01_U2055) on 
CDHF2, CDHF5, and UARSMS which addresses Y2K VMS operating system
issues.

DAAC data created for September 1998 has been loaded into the DAAC Transfer
Tables for HALOE, HRDI, NMC, PEM, and UKMO.
 
CDHF pending software upgrades: IDL 5.1, OpenIngres, UCSS 10.1, MSS 4.1,
NRT 2.5, UOAS 5.4 

                  
***********
FOT
***********
  
REPORTING PERIOD

This report covers 13 November 1998 (Orbit 39209, GMT Day 318) through 20 
November 1998 (Orbit 39298, GMT Day 324).


SPACECRAFT OPERATION

The observatory is now in Reverse Flight (Northern Hemisphere viewing) and 
is performing nominally under two-battery operations.  The instrument 
operational changes were:

              INSTRUMENT OPERATIONAL CHANGES

       Instrument        Time        Orbit     Comment
         HALOE         318/2346      39223     Off
         WINDII        318/2346      39223     Off
         PEM           319/0318      39225     Off
         PEM           320/0507      39241     On
         SUSIM         321/0834      39258     Off
         SUSIM         322/0007      39268     On
         PEM           323/2337      39298     Axis Off

The beta angle ranged between 45.5 degrees to 73.1 degrees for this report 
period. The beta angle is now increasing toward a maximum angle of 77.0 
degrees on 22 November 1998 (DOY 326).

Flight Operations continues to work with the PEM instrument to fine tune 
the operational command sequences associated with the OBC Power Monitor 
day-only operational capability.  Realtime PEM day-only troubleshooting was 
suspended when PEM went to full-time operations this week.  Testing will 
continue when PEM returns to day-only mode.

A power deficiency was experienced this week (21 November) due to 
instrument scheduling confusion.  Instrument operations were adjusted to 
assure adequate battery state-of-charge.

Spacecraft battery 1, 2, and 3 performance monitoring continues.  Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 1.0 to 1.5 degrees C.  Additional battery performance data 
for each battery on 13 November 1998 and 20 November 1998 are provided in 
Appendix D.

The clock error ranged from -6.2 to 11.1 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

%     ALERTS        =     00
%     OUT-OF-LIMITS =     03

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     06
%     HALOE   01
%     PEM     04
%     SUSIM   02
%     WINDII  01

UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     06

Three (3) Anomaly Report remained OPEN at the end of this report period 
(see Appendix E).

TRANSPONDER FREQUENCIES:
Transponder A:  98/286  -  2287.496917
Transponder B:  98/300  -  2287.498980



GROUND SYSTEM OPERATION

Four (4) operational support problems occurred this period.  Anomaly 
Reports are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/323 show the observatory data loss to be 
21 hours, 14 minutes, 49.268 seconds (an increase of 2 minutes and 56.704 
seconds since last report period).  This is a 0.0338 percent data loss 
which equals a 99.9662 percent data capture for the mission.

The increase of 2 minutes and 56.704 seconds occurred over seven (7) days:

7 1.0 minute 7.840 seconds on Day 317 due to hits in data (IP);
7 1.664 seconds on Day 318 due to hits in data (IP);
7 3.936 seconds on Day 319 due to hits in data (IP);
7 1.216 seconds on Day 320 due to hits in data and insufficient overlap;
7 1.0 minute 37.056 seconds on Day 321 due to insufficient overlap;
7 1.056 seconds on Day 322 due to hits in data; and
7 3.936 seconds on Day 323 due to hits in data (IP).

Telemetry and Command Computer (TAC) RcrashesS have diminished this report 
period.  The cause of the RcrashesS has been identified by MSOCC and 
corrective action implemented.  The problem (as reported by MSOCC - Tom 
Marsh) seems to have been produced with the data bursts experienced with 
the IP network.  The old MSS MDM systems provided data at a very periodic 
rate; whereas, the IP network provides data in bursts.  Many hardware tests 
were performed to determine why the computer would stop executing 
instructions.  No hardware problem could be found.  A conclusion was drawn 
that it may be a timing problem.  NASCOM was requested to add a two byte 
delay between NASCOM blocks.  This change seemed to improve performance.  
NASCOM was then requested on 09 November to change the clock rate of the 
data line for Q-channel data.  The following week, no additional TAC 
problems were reported.


OTHER SIGNIFICANT EVENTS

UARS SATELLITE OPERATIONS

The UARS FOT prepared and tested the Spacecraft plan for the Leonid 
encounter on the UTTS.  During the encounter, the Fixed Star Trackers 
remained ON and operational based on a re-evaluation that turn off was a 
greater risk.  The Earth Sensor 2 was turned on and the spacecraft was 
selected for earth pointing safehold (if the Onboard computer failed and 
safehold was executed).  UARS was configured on 17 November in Orbit 39262 
at 321/1452 UTC and returned to normal configuration in Orbit 39268 at 
322/0007 UTC.  No anomalies have been observed on UARS.

Investigating the feasibility of a new PMON action to change battery V/T 
curves based on loading to mitigate battery risks in sun pointing safehold.


YEAR 2000 OPERABILITY SUPPORT

UARS Test and Training Simulator (UTTS) - No change.

User Planning System (UPS) - FOT attempted to participate in a Y2K UPS/NCC-
98 test on 19 November.  However, due to some configuration problems with 
the NCC-98 system, the test has been postponed.  The test was supposed to 
allow UPS users to perform scheduling operations with NCC (via the NCC-98 
and the back-up UPS system) while a simulated clock roll-over from 1999 to 
2000 occurred..

Multi Satellite Operations Control Center (MSOCC) - No change.

Command Management System (CMS) - FOT received one (of two expected) Y2K 8-
week S/C Orbital Events file from FDF this week.  The Orbital Events file 
contained the previously missing SC_YAWMAN event.  With the receipt of this 
file, the last remaining Y2K test function (#12) for the 2000-to-2001 test 
cases (#10 and 11) has been completed.  The FOT also received a similar 
file for the 1999-to-2000 roll-over, but the file contained orbit numbers 
inconsistent with the previously generated 8-week PSAT file.  FDF will 
correct this orbit number problem and transmit a new file next week.

Flight Dynamics Facility (FDF) - see CMS paragraph.



IP NETWORK TESTING - Complete


UARS PROPULSION MODULE B/D THRUSTER LINE FILL

FOT continues to prepare the Latch valve command sequences and to plan the 
testing with the UTTS simulator in preparation for the simulation with 
hardware.  A test ATC load containing two PDB activation commands was built 
this week.  The purpose of the test ATC load was to simulate S/C thruster 
firing sequences via PDBs with the UTTS.  The test proved to be successful.

Engineering Division (Dennis Asato) advises that their engineer will not be 
available until late January 1999 ( a change from the end of November 1998) 
due to higher priority tasks.  However, the UARS FOT is now ready to 
support the tests.


UARS RE-ENGINEERING - TELEMETRY PROCESSING

Flight operations is providing assistance on both sustaining engineering 
and re-engineering activities.  FOT was contacted by re-engineering (Steve 
Liu) regarding the daily transfer of the FOTUs CMS loads to the UARS re-
engineering team.  Apparently, re-engineering is having some minor problems 
with interpreting the load formats.  In addition, re-engineering is 
experiencing a difference between the CMS generated checksums for the loads 
and the checksums generated by the new ground system after the load 
transfer is completed.

Testing of the Trending System v.1.1 release (CM-0009) continued.  More 
DR's and ER's are being generated.


MEETINGS

The next battery telecon is re-scheduled for 30 November 1998 in the power 
branch conference room.



FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is scheduled for scheduled for 13 
December 1998.

The United States Naval Observatory (USNO) issued  a Time Service 
announcement advising that the International Earth Rotation Service (IERS) 
will retard UTC time by 1.0 second at the end of December 1998. This means 
the addition of one leap second as the last second of 1998.

The next annular solar eclipse will occur on 16 February 1999 over the 
Indian Ocean, Australia and the South Pacific Ocean.


PERSONNEL CHANGES

none


Attachments:  Appendix A, Real-time Commands Sheets
              Appendix B, Out-Of-Limits & ALERT Occurrences
              Appendix C, Clock & Solar Array Rate Corrections
              Appendix D, UARS Battery Performance Data
              Appendix E, UARS Anomaly Reports



                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 20 November 1998

ORBIT       AOS         NO.     SUBSYS         REASON
-----       ---         ---     ------         -------  
39223   318/2346     98-446      HALOE      Power OFF
39223   318/2346     98-447      WINDII     Power OFF
39225   319/0318     98-448      PEM        Disable PMON Grp #10
39226   319/0501     98-449      OBC        Clk Adj fr 0.00 to 20.6 msec/day
39241   320/0507     98-450      PEM        Power ON
39258   321/0834     98-451      SUSIM      Power OFF
39262   321/1452     98-452      All        Pre-Leonid Configuration
39268   322/0007     98-453      SUSIM      Power ON
39269   322/0148     98-454      All        Post-Leonid Re-configuration
39279   322/1815     98-455      OBC        Clk Adj fr 20.6 to 41.2 msec/day
39298   323/2337     98-456      PEM        AXIS Power OFF

_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 20 November 1998

MNEMONIC         STATE         DESCRIPTION            ORBITS
---------        -----         ------------           ------
HATBAT            Y-HI     Bolometer Area Temp      39222
SOSGTEVLTG        Y-HI     G Tube Voltage           39238
HRPTSBARTEMP      Y-LO     Telescope Barrel Temp    39279-83


The following ALERT occurrences were detected:

MNEMONIC                       DESCRIPTION             ORBITS
---------                      ------------            ------
          None this report period     


_______________________________________________________________

                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 20 November 1998


                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                 CLOCK RATE CHANGE
     -----              ----                 -----------------
     39226     319/18:31 (15 Nov 98)     from 00.0 to 20.6 msec/day
     39279     322/05:55 (18 Nov 98)     from 20.6 to 41.2 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 20 November 1998


     13 Nov 1998 - GMT Day 317 Beta = 45.5 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +100.8/+84.0  -3.05/-4.62   +0.0/ +0.0    16.8     0.000   0.0
2   +33.6/-16.8  +5.15/+3.87  +28.8/-15.2    25.8     1.026  20.8
3  +145.6/+11.2  +4.19/+2.92  +28.0/-15.2    25.8     1.023  20.4


     20 Nov 1998 - GMT Day 324 Beta = 73.1 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +100.8/+78.4  -3.05/-4.31   +0.0/ +0.0    16.8    0.000    0.0
2   +16.8/-22.4  +3.87/+1.97  +18.8/-15.6    27.0    1.034   16.0
3   +78.4/+11.2  +2.60/+1.34  +18.4/-15.2    26.9    1.033   15.5


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes (V/T 5)



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 20 November 1998


                      NEW ANOMALY REPORTS GENERATED
  AR NO.   SUBSYS   ORBIT      TIME       TTR        PROBLEM/DATA LOSS
  ------   ------   -----      ----       ---        -----------------
98-092     FOT     39228     319/0824   14171     Generic Late Acquisition
98-103     FOT     39239     320/0131   20377     Negative acquisition due
                                                  to an IP problem at STGT.
98-104     FOT     39249     320/1811   20383     IP lines misconfigured
98-105     FOT     39277     322/1340   20389     Operator Error
98-105     FOT     39294     323/1820   N/A       OBC Dump errors


                 ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO.   SUBSYS  ORBIT       TIME       TTR        PROBLEM/DATA LOSS
  ------   ------  -----       ----       ---        -----------------
98-103     FOT     39239     320/01:31   20377    NEG ACQ-IP PROB
98-104     FOT     39249     320/18:11   20383    IP LINE CONF
98-105     FOT     39277     322/13:40   20389    OPN ERROR
98-106     FOT     39292     323/1500             TBL 33&34 DMP ERR


               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS  ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  -------  ------  -----      ----       ---      -----------------
                    None this report period


                      OPEN ANOMALY REPORTS
  AR NO.   SUBSYS  ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------   ------  -----      ----       ---      -----------------
98-092     FOT     Nov 98     See List   14170    GENERIC LATE ACQ
98-107     FOT     39308      324/16:40           TAC 2 PROB     
98-108     FOT     39309      324/17:23           TAC PROBLEMS


	 	SEVNTFW47