UARS Weekly Status Report

28 October 2005




********************************************************************

                UARS WEEKLY STATUS REPORT - 28 OCT 2005

********************************************************************

***********
SOLSTICE
***********

Nothing received.

***********
SUSIM
***********

Nothing received.

***********
PEM
***********

     HEPSA data files are version 2.  Currently, HEPSA data between 1991274 
and 2004273 has been reprocessed and archived at the GSFC DAAC.  HEPSA data 
between 2004274 and 2005099 has been processed and is waiting for archival
at the DAAC.

     MEPS data files are version 1.  Processed MEPS data files at the DAAC 
archive are between 1991274 and 2004259.  MEPS data between 2004260 and
2005099 has been processed and is waiting for DAAC archival.  

     HEPSB data files are version 1.  HEPSB data files between 1991274 and
1991366 have been processed and are waiting for DAAC archival.

     Processing of all PEM DAAC data files has been suspended until the
DAAC catches up with archiving all processed data files.  An error was
discovered in the DAAC IP which caused problems with DAAC access of PEM 
Level 2 data.  This was corrected at SwRI and the DAAC was successfully 
able to access SwRI.  SwRI was waiting for the DAAC to catch up on Level 2 
PEM files.  However, during this process, the DAAC again ran into access
problems.  It was found that the DAAC IP node had changed again which 
disrupted DAAC access of PEM Level 2 data.  Currently the DAAC and PEM are 
investigating the reason for another change in the DAAC IP.  A solution is 
pending.

     Checks on the PEM data availability through the DAAC have been conducted 
by SwRI.  These tests were prompted by a user of PEM data who has had trouble 
accessing the PEM data in the DAAC.  The documentation link to the PEM HEPSA 
Level 2 Document still points to the old version file pem_l2_hepsa_v01.txt 
instead of the v02 file for hepsa data.  Also, there is no MEPS entry for the 
MEPS data set.  These problems have been reported to help@daac.gsfc.nasa.gov
in mid-October.

     Tests of the AXIS1 data file formats have been successful.  The AXIS1
format design has been coded.  A test file has been generated.  A check 
program with processing scripts have also been generated.  Example binary 
read program is complete and verified.  These results have been sent to
the project.  Creation of the AXIS1 data documents for DAAC data will
begin shortly.

     PEM continues to receive NMC data files from NOAA.  No problems have 
been encountered since updates have occurred.

     The PEM data from the GUVI conjunction periods may be found at 
http://wwwpem.space.swri.edu/guvi-pem.html.  The additional electron data for 
the October and November storms of 2003 has been moved and is now located at 
http://climatology.space.swri.edu/uars_fromRudy.html.  For those users of 
SDDAS, update your UARS Meta data and these data times will appear
with full functionality.  Proton data from these storms are now located at
http://climatology.space.swri.edu/UARS_images_from_Rudy_(Apr._2004).html

     Requests have been received for storm spectral data.  Overview plots were 
produced and these plots may be found on the web at
http://climatology.space.swri.edu/UARS_images_postedJune2004.html
for the storms of October 29 of 1991, November 8-9 of 1991, April 6-7 of 2000, 
March 31 - April 1 of 2001, April 11-12 of 2001, November 6-7 of 2001, and 
November 11-12 of 2001.

     PEM has received a request for data from the super storm of November
2004.  The Dst value showed sudden commencement early on November 7, 2004
reaching a Dst value of about -380 gamma early on November 8, 2004.
PEM was not active at that time and became active late on November 8, 2004
in day only mode.  A second peak of about -280 gamma was observed on November 
11, 2004.  PEM became active in day-light only mode late on November 8.  PEM
survey spectrograms for November 8-18 of 2004 may be found at:
http://climatology.space.swri.edu/UARS_images_fromRudy.html


*Beginning of power orbit day (PEM activation): array current >5 amps, array 
     voltage >53.5 volts, and battery current >2.0 amps.  
 End of power orbit day (PEM deactivation): time in power orbit day >4 minutes,
     array current <9 amps, and battery currents <0.2 amps.
 Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

Nothing received.

***********
MPG
***********

The MPG is participating in the on-going UARS end of mission
planning activities.

The MPG continues to serve as the point-of-contact for UARS
instrument operations in support of the Science Traceability
Mission of UARS.

Daily processing of instrument Daily Activity Plans continues
with no problems.

***********
CDHF
***********

Nothing received.
                  
***********
FOT
***********

                           REPORTING PERIOD

This  report covers 15 October 2005 (Orbit 77153, GMT Day 288) through
21 October 2005 (Orbit 77260, GMT Day 294).

                         SPACECRAFT OPERATION

The observatory is now in Reverse Flight (Northern Hemisphere viewing)
and   is  performing  nominally  under  two-battery  operations.   The
instrument operational changes were:

                    INSTRUMENT OPERATIONAL CHANGES

       Instrument    Time          Orbit     Comment

       -NONE THIS REPORT PERIOD


The beta angle ranged between the angles of 38.4 degrees to 15.1
degrees for this report period.  The beta angle is now decreasing
towards a minimum angle of -2 degrees on 24 October 2005 (DOY 297).

Spacecraft battery 1, 2, and 3 performance monitoring continues.
Battery 1 remains OFF the charge relay.  TMON 45 and 46 are
maintaining the relay operations for battery 2.  Battery 2 and Battery
3 are currently maintaining greater than 23.6 V end-of-night (EON)
load bus voltage.  Battery temperatures are stable with a temperature
delta between Battery 2 and Battery 3 of 2.56 to 2.23 degrees C.
Additional battery performance data for each battery on 14 October
2005 and 21 October 2005 are provided in Appendix D.

The clock error ranged from 11.7 to -10.6 msec during this report
period.  Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT
for this report.  A summary is listed below and the details of ALERT
and Out-Of-Limits occurrences are listed in Appendix B.

    OUT-OF-LIMITS  =    00
    ALERTS         =    00

The following real-time command sheets were executed for the listed
operational element(s) during this report period (see Appendix A).


    FOT       =    07


UARS Anomaly Reports initiated during this report period are listed in
Appendix E and summarized below.

    FOT       =    03

Three (3) Anomaly Reports remained OPEN at the end of this report
period (see Appendix E).


                        GROUND SYSTEM OPERATION

Three (3) operational support problems occurred this period.  Anomaly
Reports are included in Appendix E.

The data loss calculations are no longer being supplied by Data
Capture Facility (DCF).

                       OTHER SIGNIFICANT EVENTS

                       UARS SATELLITE OPERATIONS

This week the FOT continues to closely monitor the condition of
battery 2 and battery 3.  Action was taken on the continual uneven
load sharing between battery 2 and 3.  It was determined that the PMON
calculated C/D ratio for battery 2 was not accurate.  The reason for
the inaccuracy is still not completely understood.  Manual calculation
of the battery C/D ratio using a full power orbital cycle, provided by
way of tape recorder dumps recorded during the orbit lowering burns,
gave the FOT probable cause that the C/D ratio calculation by PMON was
anywhere from 3% to 6% off.  The FOT believes that this discrepancy
started about on 12 September 2005 when the FOT changed TMON 45 and
46.  The consequence of undercharging battery 2 was that battery 3
carried the bulk of the spacecraft power load.

To remedy this undercharging of battery 2 the FOT and power branch
made minor tweaks to TMON 45 and it's timing on 17 October 2005.  The
amount of time that the TMON waited for to take battery 2 off relay
was increased from 32 seconds to 96 seconds.  This allowed roughly one
minute of "overcharge" to go into battery 2.  The results of this
change were recognized almost immediately.  Within 3 orbits of the
change, the DOD and temperature on battery 2 began increasing.  Within
3 days of the change, the FOT reduced the VT charging level from 6 to
5 since the batteries were performing much better.  Currently the
battery load sharing has been much better.  Battery 2 supplies almost
1/3 of the power load while battery 3 supplies the remaining amount.
This improved load sharing bodes well for the upcoming instrument turn
on after UARS yaws to the forward flight direction.  NASA power branch
has been providing daily support in monitoring the UARS battery
condition.  The FOT has been authorized to disable all platform and
instrument heaters on the SSPP.  This will be done at the earliest
available opportunity.

The FOT successfully completed both planned orbit-lowering burns this
week.  The orbit lowering burns on 18 October 2005 and 20 October 2005
went as expected.  Both burns started as planned at 291/1443 and
293/1209.  Each ran for 18 minutes.  The calculated duty cycle for the
burn on the 18th was 77.4%, and the duty cycle for the burn on the
20th was 77.3%.  FDF calculated that perigee was lowered by 27.1 km at
the completion of the burn on the 18th, and then lowered by an
additional 25.5 km at the completion of the burn on the 20th.  The now
elliptical orbit of UARS is approximately 557 x 383 KM.

                               MEETINGS

The FOT attended a CAM meeting on 17 October 2005.  The orbit lowering
burn script and procedures for the burn on 18 October 2005 were
reviewed and approved during this meeting.  FDF also presented their
predicted pre burn position and velocity for the upcoming burn.

The FOT attended a combined debrief and CAM meeting on 19 October
2005.  Results of the burn on 18 October 2005 were presented by FDF
and the FOT.  The orbit lowering burn script and procedures for the
burn on 20 October 2005 were reviewed and approved during this
meeting.  FDF also presented their predicted pre burn position and
velocity for the upcoming burn.





                       FUTURE SIGNIFICANT EVENTS

The next UARS Yaw slew is scheduled for 24 October 2005 (DOY 297).
This maneuver will be a Reverse to Forward Flight maneuver (Southern
Hemisphere viewing).


Attachments:   Appendix A,      Real-time Command Sheets
               Appendix B,      Out-Of-Limits   &   ALERT  Occurrences
               Appendix C,      Clock &  Solar  Array  Rate  Corrections
               Appendix D,      UARS Battery Performance Data
               Appendix E,      UARS Anomaly Reports


                              APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 21 October 2005

ORBIT   AOS        NO.      SUBSYS      REASON
-----   ---        ---      ------      ------
77196   290/1927   05-370   OBC         TMON 45 - CHANGED OOL COUNTS
77199   290/2336   05-371   OBC/CLK     CLK ADJ FR 0.0 TO -20.6 MSEC/DAY
77208   291/1305   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 1
77208   291/1334   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 2-11
77208   291/1421   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 12
77208   291/1439   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 13-23
77209   291/1519   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 25-27
77209   291/1627   05-372   MACS        ORBIT ADJUST BURN #4 - STEP 24
77217   292/0422   05-373   OBC         CLK ADJ FR -20.6 TO 0.0 MSEC/DAY
77224   292/1615   05-374   OBC         EPHEM WINOPEN / WINDEF
77236   293/1019   05-375   MACS        ORBIT ADJUST BURN #5 - STEP 1
77236   293/1059   05-375   MACS        ORBIT ADJUST BURN #5 - STEP 2-11
77237   293/1201   05-375   MACS        ORBIT ADJUST BURN #5 - STEP 12-22
77237   293/1241   05-375   MACS        ORBIT ADJUST BURN #5 - STEP 23,25-27
77238   293/1346   05-376   MPS/TMON    TMON 46 RELAY TIME / VT LEVEL 5
77239   293/1426   05-375   MACS        ORBIT ADJUST BURN #5 - STEP 24
77240   293/1631   05-377   MACS        EPHEM WINDEF


                              APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 21 October 2005

The following Out-Of-Limits occurrences were detected:

MNEMONIC       STATE   DESCRIPTION                ORBITS
--------       -----   -----------                ------
-None this report period.


The following ALERT occurrences were detected:

MNEMONIC     DESCRIPTION                          ORBITS
--------     -----------                          ------
-None this report period.



                              APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 21 October 2005

                     CLOCK DRIFT RATE ADJUSTMENTS

ORBIT          TIME                   CLOCK RATE CHANGE
-----          -----                  -----------------
77199          290/2339               CLK ADJ FR 0.0 TO -20.6 MSEC/DAY
77217          292/0430               CLK ADJ FR -20.6 TO 0.0 MSEC/DAY

                              APPENDIX D
                     UARS BATTERY PERFORMANCE DATA
                      Week ending 21 October 2005

     14 October 2005 - GMT Day 287 Beta = 41.9 deg, SA Pos = 269 deg

     DIFF V (mV)    TEMP (C)      CURR (amp)  EON V    AVE C/D  AVE
BAT  MAX/MIN        MAX/MIN       MAX/MIN     MIN      RATIO    DOD(%)
---  -------        --------      ----------  -----    -------  ------
1    728.0/ 728.0  -1.48/ -2.42  +00.0/+00.0  04.6     0.00      0.0
2   -700.0/-700.0  -0.54/ -1.79  +13.6/-06.8  25.4     1.05      3.3
3    011.2/-134.4 +10.40/ +8.40  +44.4/-25.6  25.4     1.04     25.8

     21 October 2005 - GMT Day 294 Beta = 15.1 deg, SA Pos = 269 deg

     DIFF V (mV)    TEMP (C)      CURR (amp)  EON V    AVE C/D  AVE
BAT  MAX/MIN        MAX/MIN       MAX/MIN     MIN      RATIO    DOD(%)
---  -------        --------      ----------  -----    -------  ------
1    728.0/ 728.0  -2.42/ -3.68  +00.0/+00.0  04.6     0.00      0.0
2   -700.0/-700.0  +3.23/ +2.60  +23.2/-12.0  26.1     1.06     11.1
3    224.0/  00.0  +5.79/ +4.83  +31.2/-22.8  25.8     1.02     22.9


     V/T LEVEL CHANGES
ORB#           AOS TIME   LVL FR-TO
-----          --------   ---------
77238          293/1346   LV6 -> LV5



                              APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 21 October 2005

                     NEW ANOMALY REPORTS GENERATED
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-047    FOT       77157     288/0551  30832     Generic Late Acquisition
05-047    FOT       77211     291/1944  30832     Generic Late Acquisition
05-052    FOT       77237     293/1241  41080     Post-burn late Acq-2:43
                                                  recov

                 ANOMALY CLOSURE INFORMATION RECEIVED
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-049    FOT       77094     284/0157  41076     WSGT unable to support
05-050    FOT       77100     284/1213  41080     Neg Acquisition
05-051    FOT       77101     284/1345  41080     Late Acquisition

                ANOMALY INVESTIGATION REPORTS GENERATED
AIR NO.   SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
-None this report period.

                         OPEN ANOMALY REPORTS
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-042    MPS       76339     233/2347  N/A       BATTERY 2 DIFFV -700mV
05-047    FOT       See List  Oct 05    30832     Generic Late Acquisition
05-052    FOT       77237     293/1241  41080     Post-burn late Acq-2:43
                                                  recov