UARS Weekly Status Report

14 October 2005




********************************************************************

                UARS WEEKLY STATUS REPORT - 14 OCT 2005

********************************************************************

***********
SOLSTICE
***********

Nothing received.

***********
SUSIM
***********

Nothing received.

***********
PEM
***********

HEPSA data files are version 2.  Currently, HEPSA data between 1991274 
and 2004273 has been reprocessed and archived at the GSFC DAAC.  HEPSA data 
between 2004274 and 2005099 has been processed and is waiting for archival
at the DAAC.

MEPS data files are version 1.  Processed MEPS data files at the DAAC 
archive are between 1991274 and 2004259.  MEPS data between 2004260 and
2005099 has been processed and is waiting for DAAC archival.  

HEPSB data files are version 1.  HEPSB data files between 1991274 and
1991366 have been processed and are waiting for DAAC archival.

Processing of all PEM DAAC data files has been suspended until the DAAC 
catches up with archiving all processed data files.  It was discovered
that DAAC changed the access IP node.  This caused failure accessing SwRI
to retrieve Level 2 data.  A change order at SwRI has been completed.
Tests of the interface can now be conducted.  The DAAC has successfully been
able to access SwRI again.

Checks on the PEM data availability through the DAAC have been conducted 
by SwRI.  These tests were prompted by a user of PEM data who has had trouble 
accessing the PEM data in the DAAC.  The documentation link to the PEM HEPSA 
Level 2 Document still points to the old version file pem_l2_hepsa_v01.txt 
instead of the v02 file for hepsa data.  Also, there is no MEPS entry for the 
MEPS data set.  These problems have been reported to help@daac.gsfc.nasa.gov.

Tests of the AXIS1 data file formats have been successful.  The AXIS1
format design has been coded.  A test file has been generated.  A check 
program with processing scripts have also been generated.  Example binary 
read program is complete and verified.  These results have been sent to
the project.  Creation of the AXIS1 data documents for DAAC data will
begin shortly.

PEM continues to receive NMC data files from NOAA.  No problems have 
been encountered since updates have occurred.

The PEM data from the GUVI conjunction periods may be found at 
http://wwwpem.space.swri.edu/guvi-pem.html.  The additional electron data for 
the October and November storms of 2003 has been moved and is now located at 
http://climatology.space.swri.edu/uars_fromRudy.html.  For those users of 
SDDAS, update your UARS Meta data and these data times will appear
with full functionality.  Proton data from these storms are now located at
http://climatology.space.swri.edu/UARS_images_from_Rudy_(Apr._2004).html

Requests have been received for storm spectral data.  Overview plots were 
produced and these plots may be found on the web at
http://climatology.space.swri.edu/UARS_images_postedJune2004.html
for the storms of October 29 of 1991, November 8-9 of 1991, April 6-7 of 2000, 
March 31 - April 1 of 2001, April 11-12 of 2001, November 6-7 of 2001, and 
November 11-12 of 2001.

PEM has received a request for data from the super storm of November
2004.  The Dst value showed sudden commencement early on November 7, 2004
reaching a Dst value of about -380 gamma early on November 8, 2004.
PEM was not active at that time and became active late on November 8, 2004
in day only mode.  A second peak of about -280 gamma was observed on November 
11, 2004.  PEM became active in day-light only mode late on November 8.  PEM
survey spectrograms for November 8-18 of 2004 may be found at:
http://climatology.space.swri.edu/UARS_images_fromRudy.html

*Beginning of power orbit day (PEM activation): array current >5 amps, array 
     voltage >53.5 volts, and battery current >2.0 amps.  
 End of power orbit day (PEM deactivation): time in power orbit day >4 minutes,
     array current <9 amps, and battery currents <0.2 amps.
 Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

Nothing received.

***********
MPG
***********

The MPG is participating in the on-going UARS end of mission
planning activities.

The MPG continues to serve as the point-of-contact for UARS
instrument operations in support of the UARS Science Mission.

Daily processing of instrument Daily Activity Plans continues
with no problems.

***********
CDHF
***********

Nothing received.
                  
***********
FOT
***********

                           REPORTING PERIOD

This  report covers 01 October 2005 (Orbit 76942, GMT Day 274) through
07 October 2005 (Orbit 77047, GMT Day 280).

                         SPACECRAFT OPERATION

The observatory is now in Reverse Flight (Northern Hemisphere viewing)
and   is  performing  nominally  under  two-battery  operations.   The
instrument operational changes were:

                    INSTRUMENT OPERATIONAL CHANGES

       Instrument    Time          Orbit     Comment
       -NONE THIS REPORT PERIOD


The beta angle ranged between the angles of 58.2 degrees to 61.6
degrees for this report period.  The beta angle is now decreasing
towards a minimum angle of -2 degrees on 24 October 2005 (DOY 297).

Spacecraft battery 1, 2, and 3 performance monitoring continues.
Battery 1 remains OFF the charge relay.  TMON 45 and 46 are
maintaining the relay operations for battery 2.  Battery 2 and Battery
3 are currently maintaining greater than 23.6 V end-of-night (EON)
load bus voltage.  Battery temperatures are stable with a temperature
delta between Battery 2 and Battery 3 of 10.9 to 11.5 degrees C.
Additional battery performance data for each battery on 30 September
2005 and 07 October 2005 are provided in Appendix D.

The clock error ranged from 09.9 to -10.3 msec during this report
period.  Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT
for this report.  A summary is listed below and the details of ALERT
and Out-Of-Limits occurrences are listed in Appendix B.

    OUT-OF-LIMITS  =    00
    ALERTS         =    00

The following real-time command sheets were executed for the listed
operational element(s) during this report period (see Appendix A).


    FOT       =    12


UARS Anomaly Reports initiated during this report period are listed in
Appendix E and summarized below.

    FOT       =    05

Three (3) Anomaly Reports remained OPEN at the end of this report
period (see Appendix E).


                        GROUND SYSTEM OPERATION

Five (5) operational support problems occurred this period.  Anomaly
Reports are included in Appendix E.

The data loss calculations are no longer being supplied by Data
Capture Facility (DCF).

                       OTHER SIGNIFICANT EVENTS

                       UARS SATELLITE OPERATIONS

This week the FOT continues to closely monitor the condition of
battery 2 and battery 3.  Battery 2 and 3 have not been sharing load
well since the cell failure on battery 2.  Battery 3 now carries
almost 90% of the power load while battery 2 provides the remaining
10%.  NASA power branch has been providing daily support in monitoring
the UARS battery condition.  The FOT has been authorized to disable
all platform and instrument heaters on the SSPP.  This will be done at
the earliest available opportunity.  The FOT also changed VT levels
from 7 to 6 because of the high approaching high beta.  The FOT will
revert back to VT-7 at a future date based on power needs.

The FOT successfully completed two-planned orbit lowering burns this
week.  The first orbit lowering burn on 04 October 2005 went extremely
well.  The burn started as planned at 277/1709 and ran for 18 minutes.
The calculated duty cycle for the burn was 78.1%.  FDF calculated that
perigee was lowered by 38 km at the completion of this burn.

The second orbit lowering burn on 06 October 2005 went as expected.
The burn started as planned at 179/1507 and ran for 18 minutes.  The
calculated duty cycle for the burn was 77.7%.  FDF calculated that
perigee was lowered by 32.8 km at the completion of this burn.


                               MEETINGS

The FOT attended a pre-burn CAM meeting on 03 October 2005.  The orbit
lowering burn script and procedures were reviewed and approved during
this meeting.  FDF also presented their predicted post burn position
and velocity based on the engineering calibration burns done.

The FOT attended a combined post burn de-brief and CAM meeting on 05
October 2005.  The FOT and FDF presented their analysis of the 18-
minute burn that occurred on 04 October 2005.  The FOT re-sequenced a
few commands in the burn script in order to minimize the time needed
before the burn start time.  The FOT now only needs 3 minutes of
commanding time from the start of the pass to be able to fire the
thrusters, and 5 minutes to safe the propulsion module before LOS of
the burn pass.


                       FUTURE SIGNIFICANT EVENTS

The next UARS Yaw slew is scheduled for 24 October 2005 (DOY 297).
This maneuver will be a Reverse to Forward Flight maneuver (Southern
Hemisphere viewing).

UARS has been given permission to executing the scheduled 18-minute
burns on 12 October 2005.  Authorization has also been given to
complete as many burns as possible in the current yaw direction.  The
FOT will proceed with the remaining burns scheduled for 12 October
2005, 18 October 2005, and 20 October 2005.


Attachments:     Appendix A,              Real-time Command Sheets
                 Appendix B,              Out-Of-Limits & ALERT
Occurrences      Appendix C,              Clock & Solar Array Rate
Corrections      Appendix D,              UARS Battery Performance Data
                 Appendix E,              UARS Anomaly Reports
                 
                              APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 07 October 2005

ORBIT   AOS        NO.      SUBSYS      REASON
-----   ---        ---      ------      ------
76949   274/1227   05-351   OBC/CLK     CLK ADJ FR 20.6 TO 0.0 MSEC/DAY
76981   276/1601   05-352   OBC         TMON 46 TIME DELAY CHANGED 16:40
76983   276/1857   05-353   OBC/CLK     CLK ADJ FR 0.0 TO 20.6 MSEC/DAY
76995   277/1417   05-354   MACS        END OF MISSION BURN 1 STEP 3,22
76996   277/1519   05-354   MACS        EOM BURN 1 STEP 1
76996   277/1558   05-354   MACS        EOM BURN 1 STEP 2-10
76996   277/1558   05-355   MACS        ESAM 2 ON
76997   277/1701   05-354   MACS        EOM BURN 1 STEP 11-24
76997   277/1741   05-354   MACS        EOM BURN 1 STEP 23
76998   277/1819   05-355   MACS        ESAM 2 OFF
76998   277/1819   05-356   MPS         VT LEVEL 7 TO VT LEVEL 6
76998   277/1854   05-356   TMON        TMON 46 TIME DELAY 5:30
77000   277/2136   05-357   TMON        TMON 46 TIME DELAY 12:30
77012   278/1629   05-358   OBC         LOAD NOMINAL EPH TOLERANCES
77025   279/1321   05-359   MACS        EOM BURN #2 - STEP 1
77025   279/1357   05-359   MACS        EOM BURN #2 - STEP 2-11
77025   279/1357   05-360   OBC/CLK     CLK ADJ FR 20.6 TO 0.0 MSEC/DAY
77026   279/1457   05-359   MACS        EOM BURN #2 - STEP 12-23
77026   279/1537   05-359   MACS        EOM BURN #2 - STEP 24-27
77026   279/1537   05-361   OBC         EPH LOAD REJECT CORRECTION
77029   279/2014   05-362   OBC         DEFAULT EPH TOLERANCES


                              APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 07 October 2005

The following Out-Of-Limits occurrences were detected:

MNEMONIC       STATE   DESCRIPTION                ORBITS
--------       -----   -----------                ------
-None this report period.


The following ALERT occurrences were detected:

MNEMONIC     DESCRIPTION                          ORBITS
--------     -----------                          ------
-None this report period.



                              APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 07 October 2005

                     CLOCK DRIFT RATE ADJUSTMENTS

ORBIT          TIME                   CLOCK RATE CHANGE
-----          -----                  -----------------
76949          274/1231               CLK ADJ FR 20.6 TO 0.0 MSEC/DAY
76983          276/1859               CLK ADJ FR 0.0 TO 20.6 MSEC/DAY
77025          279/1357               CLK ADJ FR 20.6 TO 0.0 MSEC/DAY


                              APPENDIX D
                     UARS BATTERY PERFORMANCE DATA
                      Week ending 07 October 2005

     30 September 2005 - GMT Day 273 Beta = 58.2 deg, SA Pos = 269 deg

        DIFF V (mV)    TEMP (C)       CURR (amp)    EON V    AVE C/D   AVE
BAT     MAX/MIN        MAX/MIN        MAX/MIN       MIN      RATIO     DOD(%)
---     -------        --------       ----------    -----    -------   ------
1        728.0/ 728.0  -1.79/ -2.42   +00.0/+00.0   04.6     0.00       0.0
2       -700.0/-700.0  -1.48/ -2.42   +08.0/-03.2   26.4     1.09       2.2
3        084.0/ 033.6  +10.40/ +9.06  +38.0/-24.0   26.4     1.04      27.6

     07 October 2005 - GMT Day 280 Beta = 61.2 deg, SA Pos = 269 deg

       DIFF V (mV)    TEMP (C)       CURR (amp)    EON V     AVE C/D   AVE
BAT    MAX/MIN        MAX/MIN        MAX/MIN       MIN       RATIO     DOD(%)
---    -------        --------       ----------    -----     -------   ------
1       728.0/ 728.0  -1.79/ -3.05   +00.0/+00.0   04.6      0.00       0.0
2      -700.0/-700.0  -1.17/ -2.42   +09.6/-05.6   25.8      1.08       2.3
3       324.8/ 056.0  +9.73/ +7.74   +37.6/-27.6   25.8      1.05      25.8


     V/T LEVEL CHANGES
ORB#           AOS TIME   LVL FR-TO
-----          --------   ---------
76998          277/1819   LV7 -> LV6



                              APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 07 October 2005

                     NEW ANOMALY REPORTS GENERATED
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-047    FOT       76954     274/2023  30832     Generic Late Acquisition
05-047    FOT       76974     276/0440  30832     Generic Late Acquisition
05-047    FOT       76992     277/0939  30832     Generic Late Acquisition
05-047    FOT       76993     277/1119  30832     Generic Late Acquisition
05-048    FOT       76997     277/1741  41006     Post-Burn Late Acq (05:04)

                 ANOMALY CLOSURE INFORMATION RECEIVED
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-044    FOT       See List  Sept 05   30832     Generic Late Acquisition

                ANOMALY INVESTIGATION REPORTS GENERATED
AIR NO.   SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
-None this report period.

                         OPEN ANOMALY REPORTS
AR NO.    SUBSYS    ORBIT     TIME      CDS       PROBLEM/DATA LOSS
------    ------    -----     ----      ---       -----------------
05-042    MPS       76339     233/2347  N/A       BATTERY 2 DIFFV -700mV
05-047    FOT       See List  Oct 05    30832     Generic Late Acquisition
05-048    FOT       76997     277/1741  41006     Post-Burn Late Acq (05:04)