UARS Weekly Status Report

28 August 1998





********************************************************************

                UARS WEEKLY STATUS REPORT - 28 August 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, collecting solar data on all 
available orbital tracking periods and stellar calibration observations, 
whenever possible.  

***********
SUSIM
***********

SUSIM has successfully gathered its normal solar, offset, and occulation
data during this past week without apparent problems.

***********
PEM
***********

     PEM was not active

     GSFC has proposed an OBC operation plan for the activation of PEM boom 
instruments during the daylight portions of every orbit.  This OBC operation 
plan is accepted by PEM.  PEM has proposed a series of test procedures for 
activation and is waiting response from GSFC.  PEM is also waiting for GSFC
scheduling and implementation of the OBC plan and its operation test procedures.

***********
HALOE 
***********

HALOE Status
August 28, 1998

HALOE was turned on at the beginning of day today.  All engineering
parameters are nominal.  Science channel performance is being evaluated,
but initial look indicates they are working properly.

***********
MLS
***********

The instrument is now off as scheduled. 

***********
HRDI
***********

Nothing received.

***********
WINDII
***********

Nothing received.

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues 
with no other problems.  The MPG continues to assist the Project 
Scientist with the scheduling of instrument operations.

***********
CDHF
***********

The CDHF processed current day data through level 3 for all active
   instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.
           
             95 days HAL (4.80) PROD (L1)    (1873R-1232C-25F=616L)
             44 days HAL (4.80) PROD (L3)    (1873R-714C=1159L)
             80 days SOL (4.62) PROD (L2-L3) (2349R-1247C=1102L)
              2 days SUS (7.00) ENG          (2R-2C=0L)  

The CDHF is preparing for the upgrade of current FORTRAN compiler, 
version 6.3, to version 6.5.  A statement of impact has been 
has been sent to the user community.  Plans to install, following 
response to user correspondence,  were scheduled for the
week of the 24th of August, however network problems took precedence.
  
The CDHF worked with NSI personnel and the UARS Network Manager
toward the resolution of network problems affecting entire gateway.
      
CDHF pending software upgrades: IDL 5.1, OpenIngres, Fortran V6.5.  
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 15 August 1998 (Orbit 37846, GMT Day 227) through 21 
August 1998 (Orbit 37950, GMT Day 233).


SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) and 
is performing nominally under two-battery operations.  The instrument 
operational changes were:

                   INSTRUMENT OPERATIONAL CHANGES

     Instrument         Time         Orbit        Comment
     PEM              227/0112       37860        AXIS Off
     HRDI             230/2240       37905        Low Power
     WINDII           231/0024       37906        On
     HALOE            233/1524       37945        Off

The beta angle ranged between the angles of 46.4 degrees to 16.5 degrees 
for this report period.  The beta angle is now decreasing toward a minimum 
angle of 0.0 degrees on 25 August 1998 (DOY 237).

Five (5) additional SSPP SOLSTICE Offset sequence were performed this week 
on GMT days 228-232 at the request of SUSIM operations (and with the 
agreement of SOLSTICE operations).  The offsets were identical to the 
regular SSPP SOLSTICE Offset sequence, which is nominally scheduled once 
per week.

Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 0.9 to 1.3 degrees C.  Additional battery performance data 
for each battery on 14 August 1998 and 21 August 1998 are provided in 
Appendix D.

The clock error ranged from 10.2 to -12.8 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

-     ALERTS          =     01
-     OUT-OF-LIMITS   =     05

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

-     FOT     03
-     HRDI    02
-     HALOE   01
-     PEM     01
-     WINDII  01

UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

-     FOT     04

One (2) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
     Transponder A:  98/210  -  2287.496941
     Transponder B:  98/211  -  2287.499161


GROUND SYSTEM OPERATION

One (1) operational support problems occurred this period.  Anomaly Reports 
are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/232 show the observatory data loss to be 
21 hours, 04 minutes, 45.332 seconds (an increase of eighteen (18) minutes 
and 34.784 seconds since last report period).  This is a 0.0348 percent 
data loss which equals a 99.9652 percent data capture for the mission.

The increase of 18 minutes and 34.784 seconds occurred over six days:

- 18:29.472 seconds on Day 227 due to insufficient overlap and degraded 
data;
- 1.216 seconds on Day 228 due to insufficient overlap and line errors;
- 2.592 seconds on Day 229 due to line errors and hits in data;
- 0.160 seconds on Day 230 due to line errors;
- 1.120 seconds on Day 231 due to line errors; and
- 0.224 seconds on Day 232 due to line errors.

Applications Processor (AP) ground system software testing has been 
suspended waiting release of an operational pack containing version 10.11.

FOT performed an operational pack "cleanup" this week in order to 
facilitate a baseline the new Ground Software using the current operational 
pack.  Redundant OBC dumps on the pack were eliminated keeping the required 
one set per month.  This resulted in a substantial disk space saving.


OTHER SIGNIFICANT EVENTS

UARS SATELLITE OPERATIONS

FOT continues to improve a power profile for UARS based on the current 
status of the Modular Power System.

The FOT is investigating an incident and maybe a second incident of high 
noise at the beginning of playback of the Narrowband Tape Recorder (NBTR) 
in an attempt to identify whether it is due to flight equipment or ground 
equipment.

Flight operations is investigating an alternate to sun pointing safe hold 
which can provide better protection for a two battery power subsystem.  The 
FOT is also attempting to define a one battery scenario which would save 
the spacecraft and allow a single instrument to operate or the SSPP 
instruments to operate with all other instruments completely OFF.


YEAR 2000 OPERABILITY SUPPORT

UARS Test and Training Simulator (UTTS) No change in status.

User Planning System (UPS) - No change in status.

Multi Satellite Operations Control Center (MSOCC) - No change in status.

Command Management System (CMS) - The FOT worked with CMS Year 2K Test Team 
representatives Daya Srivastava and Sidney Kirschner this week in an 
continuing effort to get the back-up CMS system ready for testing.  Due to 
an increased disk quota for the test account on UCMSB, the FOT was able to 
continue copying necessary support files from the prime CMS to the back-up 
system.  In addition, the FOT worked with Mr. Kirschner in attempting to 
retrieve FDF Year 2K planning aids from a 4mm tape generated in the FORMATS 
Test Facility.  Due to incompatibilities between the system that was used 
to generate the tape and the CMS system, the files could not be downloaded 
onto UCMSB.  The FOT and the Year 2K test team are investigating other 
alternatives to getting the FDF data onto the back-up UCMS system.

There was no Year 2K CMS status meeting this week.

Flight Dynamics Facility (FDF) - Year 2K planning aids have been generated.

OBC PMON FLIGHT SOFTWARE UPDATE

Flight Software - The Flight Software is complete.

Ground Support Software - Complete.  The Applications Processor operational 
disk pack is being generated.

Verification Testing - Testing of the operations pack compilation of the 
software will be required prior to uplink.

IP NETWORK TESTING

Space Network (SN) - NCC I/P testing was conducted during TDRSS contact at 
232/15:22 to 225/15:36.  Initially, no NCC data and no acknowledgments 
GCMRUs were received.  Later in the contact, good acknowledgment for our 
GCMRUs were received but ODM data was present.  The problem is currently 
under investigation and additional testing will be scheduled.

Testing with the NCC 98 system to support routine flight operations is 
being planned.

Deep Space Network (DSN) and Ground Spaceflight Tracking and Data Network 
(GSTDN) - Working with the DSN test lead for I/P testing to verify UARS 
emergency backup sites.

UARS PROPULSION MODULE B/D THRUSTER LINE FILL

The B/D thruster refill effort continues.  Latch valve testing at Eaton has 
been completed and preliminary results given to the GSFC Propulsion Branch.  
A more comprehensive Eaton report is expected to follow.  The ground line 
fill tests are still planned to be executed after analysis of the Eaton 
data.

Jackson and Tull were authorized to go forward on the electronics for latch 
valve operation pending release of further funds.

UARS RE-ENGINEERING - TELEMETRY PROCESSING

Flight operations is providing support to the re-engineering effort to 
process the UARS telemetry on the TOMS/EP control center computer system.

UARS COMMAND RE-HOST PHASE 1 DEMONSTRATION

Flight operations continues to support the update of the Lockheed Martin 
SCS-21 control center system to support a phase 1 feasibility 
demonstration.  FOT provided a cross reference of ODM block data to the ODM 
display page.

The SCS-21 equipment arrived at GSFC on 17 August 1998 and is being 
assembled and operationally checked.

NCC 98 availability for SCS-21 testing is limited to a single 8-hour-block 
during the week of 24 August 1998.



MEETINGS

The FOT met with the Project Scientist and Deputies on 19 August 1998 to 
brief them on the UARS subsystem status.  Various contingencies and 
possible reaction were also discussed.

No UARS Battery telecon was held this week.  The next telecon has been 
scheduled for 25 August 1998 at 1:00 pm.


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is scheduled for scheduled for 25 August 
1998.


PERSONNEL CHANGES

None


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports



                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 21 August 1998

ORBIT      AOS         NO.     SUBSYS       REASON
-----      ---         ---     ------       -------  
37848   227/0431     98-298    OBC      Clk Adj fr 20.6 to 0.00msec/day
37860   227/0112     98-299    PEM      AXIS      Power Off
37880   229/0637     98-300    OBC      Clk Adj fr 0.00 to 20.6msec/day     
37905   230/2240     98-301    OBC      Clk Adj fr 20.6 to 0.00msec/day
37905   230/2240     98-302    HRDI     Low Power Mode
37906   231/0024     98-303    WINDII   Power ON               
37944   233/1415     98-304    HRDI     Htr. Cycle to 75 amp-min
37945   233/1524     98-305    HALOE    Power OFF



_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 21 August 1998

MNEMONIC      STATE      DESCRIPTION                     ORBITS
---------     -----      ------------                    ------
WIEUTEMP     Y-HI     WINDII EU Temperature     37868,73,74,876-906
HRPTSPBIMON  Y-HI     PTS Pulse Bus Cur. Mon    37892
HRIFESURVTMP Y-HI     IFE Survival Temp         37907
HRPSEQBIMON  Y-HI     HRDI PSE Q/B Cur. Mon.    37942-4
QTSISAIF     Y-HI     SSPP Baseplate SISA I/F   37942-4



The following ALERT occurrences were detected:

MNEMONIC                DESCRIPTION                      ORBITS
---------               ------------                     ------
WISRCBBS     Broad Band Source Op (during Turn-on)     37907



_______________________________________________________________

                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 21 August 1998


                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                 CLOCK RATE CHANGE
     -----              ----                 -----------------
     37848     227/04:38 (15 Aug 98)     from 20.6 to 00.0 msec/day
     37880     229/06:43 (17 Aug 98)     from 00.0 to 20.6 msec/day
     37905     230/22:42 (18 Aug 98)     from 20.6 to 00.0 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 21 August 1998


     14 Aug 1998 - GMT Day 226 Beta = 46.4 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-4.31  +0.0/ +0.0    18.1     0.000   0.0
2   +22.4/-22.4   +6.11/+4.51 +28.4/-16.0    25.1     1.024  21.6
3   +33.6/-16.8   +5.15/+3.23 +27.2/-16.0    25.0     1.026  21.1

     21 Aug 1998 - GMT Day 233 Beta = 16.5 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-3.99  +0.0/ +0.0    18.1     0.000   0.0
2   +67.2/-0.0    +7.09/+4.83 +31.2/-16.4    23.8     1.023  23.1
3   +39.2/-33.6   +5.79/+3.87 +30.4/-16.8    23.8     1.023  22.4


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes (V/T 5)



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 21 August 1998


                      NEW ANOMALY REPORTS GENERATED
  AR NO. SUBSYS  ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------ ------  -----      ----       ---      -----------------
98-047   FOT     37862     228/0253   14170   Generic Late Acquisition
98-048   FOT     37870     228/1555   N/A     RCDR in PLBK at LOS     
98-050   FOT     37932     232/1840   N/A     degraded 512 kbps dump
98-051   FOT     37938     223/0459   N/A     TAC N0-8 Crashed


                ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO. SUBSYS  ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------ ------  -----      ----       ---      -----------------
98-046  FOT     37742     220/0116   20129  TELEMETRY DROPOUT
98-048  FOT     37870     228/1155          NBR NOT IN REC
98-049  FOT     37831     226/0114          NOISY NBR P/B
98-050  FOT     37932     232/1840          NOISY NBR P/B
98-051  FOT     37938     233/0500          TAC 8 CRASH


               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS       ORBIT     TIME       TTR      PROBLEM/DATA LOSS
  -------  ------       -----     ----       ---      -----------------
                    None this report period


                        OPEN ANOMALY REPORTS
  AR NO.  SUBSYS       ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------  ------       -----      ----       ---      -----------------
98-045     FOT     See list Aug 1998     14170 Generic Late Acquisition
98-047     FOT     37856    227/1713     20149 NOISY NBR P/B