UARS Weekly Status Report

14 AUGUST 1998




********************************************************************

                UARS WEEKLY STATUS REPORT - 14 AUG 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, collecting solar data on all 
available orbital tracking periods and stellar calibration observations, 
whenever possible.

***********
SUSIM
***********

SUSIM has successfully gathered its normal solar, offset, and occulation
data during this past week.  The yearly calibration using all four
deuterium lamps was completed without serious problems.

***********
PEM
***********

Nothing received.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

The MLS team has continued to work towards determining a useful new operating
mode for MLS.  Although there are some encouraging signs, we are not there
yet.  A couple of times the scan machanism has become stuck, but we have freed
it.  The instrument is now off as scheduled. 

***********
HRDI
***********

Nothing received.

***********
WINDII
***********

WINDII is currently off, awaiting activation on August 19, 1998.

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues
with no problems.  The MPG continues to assist the Project
Scientist with the scheduling of instrument operations.

***********
CDHF
***********

The CDHF has received a total of 406 CD-ROM requests as of 14-August-1998.
There were two orders received and shipped.
                                       
The CDHF processed current day data through level 3 for all active
 instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.           
            100 days HAL (4.80) PROD (L1)    (1873R-1020C-18F=835L)
             61 days HAL (4.80) PROD (L3)    (1873R-648C=1225L)
            111 days SOL (4.62) PROD (L2-L3) (2349R-1053C=1296L)
              2 days SUS (7.0)  ENG          (2R-2C=0L)
              0 days WIN (5.10) ENG          (1R-1F=1L)
  
The CDHF is preparing for the upgrade of the current FORTRAN compiler, version
6.3, to version 6.5.  A statement of impact has been drafted and sent to the
user community this week.
  
The CDHF continues to identifying all patches required on the current UARS VMS
cluster operating systems for Y2K compliance. A schedule for implementing
these releases is being developed.

CDHF pending software upgrades: IDL 5.1, OpenIngres, Fortran V6.5 
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 01 August 1998 (Orbit 37636, GMT Day 213) through 07 
August 1998 (Orbit 37740, GMT Day 219).


SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) and 
is performing nominally under two-battery operations.  The instrument 
operational changes were:

                 INSTRUMENT OPERATIONAL CHANGES

     Instrument        Time       Orbit         Comment
        PEM          213/2226     37650         Zeps Off
       SUSIM         216/0105     37682         Detect. Off
        MLS          217/2058     37709         Scan Test

The beta angle ranged between the angles of 62.4 degrees to 71.5 degrees 
for this report period.  The beta angle is now decreasing toward a minimum 
angle of 0.0 degrees on 25 August 1998 (DOY 237).

Four (4) additional SSPP SOLSTICE Offset sequences were performed this week 
on GMT days 215 through 218 at the request of SUSIM operations (and with 
the agreement of SOLSTICE operations).  The offsets were identical to the 
regular SSPP SOLSTICE Offset sequence, which is nominally scheduled once 
per week.

Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 0.9 to 1.3 degrees C.  Additional battery performance data 
for each battery on 31 July 1998 and 07 August 1998 are provided in 
Appendix D.

The clock error ranged from 11.1 to -10.5 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

%     ALERTS           =     00
%     OUT-OF-LIMITS    =     02

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     04
%     MLS     04
%     PEM     01
%     SUSIM   01


UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     01

One (1) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
     Transponder A:  98/210  -  2287.496941
     Transponder B:  98/211  -  2287.499161


GROUND SYSTEM OPERATION

No (0) operational support problems occurred this period.  Anomaly Reports 
are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/218 show the observatory data loss to be 
20 hours, 45 minutes, 50.356 seconds (an increase of 7.872 seconds since 
last report period).  This is a 0.0345 percent data loss which equals a 
99.9655 percent data capture for the mission.

The increase of 7.872 seconds occurred over four days:

7 0.160 seconds on Day 212 due to line errors,
7 0.160 seconds on Day 214 due to line errors,
7 7.296 seconds on Day 215 due to insufficient overlap, and
7 0.256 seconds on Day 218 due to line errors.

Some of the operational CMS workstations temporarily lost power on 07 
August due to an unscheduled power outage in Building 32.  This resulted in 
the automatic initiation of a Rshadow disk mergeS process on the CMS.  Once 
the shadow merge was completed, the CMS appeared to be operating normally, 
although CMS processing was extremely slow during the merge process.

Applications Processor (AP) ground system software testing has been 
suspended waiting release of an operational pack containing version 10.11.


OTHER SIGNIFICANT EVENTS

UARS SATELLITE OPERATIONS

FOT continues to improve a power profile for UARS based on the current 
status of the Modular Power System.

An FOT Standard Operating Procedure is being developed outlining how to 
restore files to the CMS from the incremental or full back-up tapes.  The 
SOP is still under review, and should be completed sometime next week.

Flight operations is investigating an alternate to sun pointing safe hold 
which can provide better protection for a two battery power subsystem.  The 
FOT is also attempting to define a one battery scenario which would save 
the spacecraft and allow a single instrument to operate or the SSPP 
instruments to operate with all other instruments completely OFF.

YEAR 2000 OPERABILITY SUPPORT

UARS Test and Training Simulator (UTTS) - has been analyzed and determined 
to be 2000 compatible.

User Planning System (UPS) - The UPS software will be year 2000 compatible 
with Release 11 Build 3 scheduled for development in September 1998 (The 
Integrator, June 1998).

Multi Satellite Operations Control Center (MSOCC) - flight operations is 
Rstanding byS to provide support to this CNMOS effort.  The UARS simulator 
is available on request.

Command Management System (CMS) - FOT supported the CMS Year 2K test team, 
as well as the CMS software maintenance team, in determining the status of 
the back-up CMS system.  Apparently, the login files for the various 
accounts on that system are not presently set-up to support operational 
type testing.  The CMS system managers will be contacted as soon as 
possible to get this problem rectified.

In addition, the status of the two pending CMS software releases (R7B1V1 
and R7B1V2) was also investigated.  It appears that both software releases 
are on the back-up CMS system, but the releases must be RinstalledS before 
any testing of them can be performed.

FOT met with Year 2K test team lead (Sidney Kirschner) to discuss 
additional hands-on training on the CMS, as well as development of the Year 
2K test plan.  These meeting will probably be frequent throughout the 
duration of the Year 2K testing.

Flight Dynamics Facility (FDF) - The FOT and Test Team have both requested 
test planning aids from FDF, but no products have been delivered.  These 
products are essential to testing the CMS software.

OBC PMON FLIGHT SOFTWARE UPDATE

Flight Software - The Flight Software is complete.

Ground Support Software - Complete and delivered to the library. The 
Applications Processor operational disk pack is being generated.

Verification Testing - The flight software and the test pack version of the 
ground support software (Applications Processor) have been tested.  Testing 
of the operations pack compilation of the software will be required prior 
to uplink.

IP NETWORK TESTING

Space Network (SN) - Testing of command and telemetry with the UARS 
simulator completed successfully.  NCC testing has been attempted but 
aborted due to line configuration problems.  NCC testing is on hold until 
the MSOCC line configuration problem can be resolved.  Performance testing 
with the spacecraft will be scheduled after NCC test completion.

Testing with the NCC 98 system to support routine flight operations is 
being planned.

Deep Space Network (DSN) - UARS emergency backup sites not scheduled at 
this time.  Investigating the procedure.

Ground Spaceflight Tracking and Data Network (GSTDN) - UARS emergency 
backup sites not scheduled at this time.  Investigating the procedure.

UARS PROPULSION MODULE B/D THRUSTER LINE FILL

The B/D thruster refill effort continues.  Latch valve testing at Eaton is 
delayed due to the unavailability of key personnel.  Results are expected 
in late August 1998.  The Eaton Test results will be used to determine the 
timing of the latch valve open times for the GSFC hardware fill test.  The 
command timing will be designed for execution from the UTTS by the UARS 
FOT.  The Propulsion Module Electronics (PME) simulation circuit design is 
complete but part ordering and further work is on hold until funding issues 
can be resolved.

UARS RE-ENGINEERING - TELEMETRY PROCESSING

Flight operations is providing support to the re-engineering effort to 
process the UARS telemetry on the TOMS/EP control center computer system.  
Question are being researched and answers provided regarding details of the 
current control center software (MSOCC) and the off-line analysis software 
resident on the Central Data Handling Facility (CDHF).

UARS COMMAND RE-HOST PHASE 1 DEMONSTRATION

Flight operations continues to support the update of the Lockheed Martin 
SCS-21 control center system to support a phase 1 feasibility 
demonstration.  Requirements have been provided and questions are being 
researched and answers provided for detail implementation issues.  A 
demonstration test script has been generated and successfully tested with 
the UARS simulator.

The NCC portion of the test script was tested with the NCC 98 system on 05 
August 1998.  This test was complicated by line configuration problems 
connecting the NCC 98 system but completed successfully.  The test script 
is now considered complete.


MEETINGS

The FOT attended a weekly CMS Year 2K status meeting (hosted by Carey 
Myers) on 06 August 1998.  Topics of discussion at the meeting were the 
current status of the back-up CMS system, the status of the Year 2K testing 
itself, and the timeline and deadlines related to the testing.

No UARS Battery telecon was held this week.  The next telecon has been 
scheduled for 25 August 1998 at 1:00 pm.


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is scheduled for scheduled for 25 August 
1998.


PERSONNEL CHANGES

None


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports



                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 07 August 1998

ORBIT      AOS           NO.     SUBSYS        REASON
-----      ---           ---     ------       -------  
37637     213/0154     98-276    OBC       Clk Adj fr 20.6 to 41.2 msec/day
37650     213/2226     98-277    PEM       ZEPS Power OFF
37666     215/0059     98-278    OBC       Clk Adj fr 41.2 to 20.6 msec/day
37682     216/0105     98-279    SUSIM     Turn off one detector
37688     216/1119     98-280    OBC       Clk Adj fr 20.6 to 41.2 msec/day
37694     216/2054     98-281    MLS       MLS Stop/Run
37697     217/0224     98-282    MLS       MLS STOP/RUN
37709     217/2058     98-283    MLS       MLS Scan Test
37739     219/2106     98-284    OBC       Clk Adj fr 41.2 to 20.6 msec/day 
37740     219/2337     98-285    MLS       Start Nominal Scan Program



_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 07 August 1998

MNEMONIC           STATE       DESCRIPTION                     ORBITS
---------          -----       ------------                    ------
MLSSCANACTTMP      Y-LO     MLS Scan Actuator Temp     37697
MLSSCANACTTMP      R-LO     MLS Scan Actuator Temp     37697



The following ALERT occurrences were detected:

MNEMONIC              DESCRIPTION                           ORBITS
---------             ------------                          ------
                  None this report period




_______________________________________________________________

                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 07 August 1998


                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                 CLOCK RATE CHANGE
     -----              ----                 -----------------
     37637     213/02:01 (01 Aug 98)     from 20.6 to 41.2 msec/day
     37666     215/01:08 (03 Aug 98)     from 41.2 to 20.6 msec/day
     37688     216/11:24 (04 Aug 98)     from 20.6 to 41.2 msec/day
     37739     219/21:15 (07 Aug 98)     from 41.2 to 20.6 msec/day



_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 07 August 1998


     31 Jul 1998 - GMT Day 212 Beta = 62.4 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.68/-4.94   +0.0/ +0.0   18.1    0.000    0.0
2   +16.8/-22.4   +4.51/+2.92  +22.4/-16.0   26.2    1.025   19.8
3   +44.8/-11.2   +3.23/+1.97  +22.0/-15.2   26.2    1.029   19.3

     
     07 Aug 1998 - GMT Day 219 Beta = 71.5 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-4.62   +0.0/ +0.0   18.1    0.000     0.0
2   +11.2/ -33.6  +3.87/+1.97  +19.2/-16.0   26.7    1.034    16.8
3   +22.4/ -22.4  +2.60/+1.03  +18.4/-15.2   26.6    1.031    16.3


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes (V/T 5)



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 07 August 1998


                    NEW ANOMALY REPORTS GENERATED
  AR NO.   SUBSYS    ORBIT      TIME       TTR    PROBLEM/DATA LOSS
  ------   ------    -----      ----       ---    -----------------
98-045     FOT   See list   Aug 1998     14170  Generic Late Acquisition


                ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO.   SUBSYS    ORBIT      TIME       TTR    PROBLEM/DATA LOSS
  ------   ------    -----      ----    ---       -----------------
98-044     FOT   See list   Jul 1998     14170  Generic Late Acquisition


               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS    ORBIT      TIME       TTR    PROBLEM/DATA LOSS
  -------  ------    -----      ----       ---    -----------------
                    None this report period


                      OPEN ANOMALY REPORTS
  AR NO.   SUBSYS    ORBIT      TIME       TTR    PROBLEM/DATA LOSS
  ------   ------     -----      ----      ---    -----------------
98-045     FOT    See list  Aug 1998     14170  Generic Late Acquisition