******************************************************************** UARS WEEKLY STATUS REPORT - 20 JUL 2001 ******************************************************************** *********** SOLSTICE *********** SOLSTICE continues to operate normally, taking solar data on all available orbital tracking periods and stellar calibration observations whenever possible. We continue to gather enough data to meet all the SOLSTICE science objectives during this period of reduced tape recorder operations. *********** SUSIM *********** SUSIM had a commanding error which caused it to miss two MgII index scans. This now has been corrected. Otherwise, SUSIM has completed its daily solar scans this past week during periods of predicted UARS telemetry. *********** ACRIM *********** Following a loss of power in early May, the ACRIM instrument has not responded to power-up commands. The ACRIM team is working on a scenario of power-ups and downs to test the apparent inability of the instrument power supply to activate. The ACRIM2 total solar irradiance database has been re-processed and is complete up to the May 2001 power loss. The new processing scheme utilizes improved algorithms developed for the ACRIMSAT/ACRIM3 experiment whose science mission began in April 2000. Reprocessing has found additional results and more degradation comparisons that have resulted in a much improved version of the total solar irradiance results from the experiment. These results are available at the ACRIM Science Team web site (http://acrim.com) and at NASA's LaRC and GSFC DAAC's. *********** PEM *********** ***** ALL PEM COMMUNICATION SHOULD NOW BE THROUGH THE PEM2K:: NODE ***** The PEM team reports that the PEM:: node computer has failed and has been taken off line. PEM:: appears to have hardware problems that take the system down every few hours. Automatic transfer NRT tests to PEM2K from both CDHF2 and CDHFB have succeed and the NRT files have been verified against those captured by PEM, which confirm the NRT process is correct. Thus, PEM confirms NRT data from CDHFB. Thanks to Steve Bove for his work assisting PEM with this process. PEM/AXIS was activated in activated in full power mode on July 3. At the current time, AXIS is not generating energy deposition. SwRI is looking into this. Tests of AXIS production code on the rehost computer are continuing. At the present time, PEM energy deposition from its spectrometers is not being generated. Recent data configuration changes have affected PEM software causing multiple failures. These failures are being reviewed by the PEM team. In order to correct for new telemetry requirements, PEM will need to update processing code with a patch delivery. The delivery patch may include changes which would allow the PEM software to execute on a DEC Alpha machine. GSFC is helping PEM with some DEC Alpha particulars which have caused PEM level 3 code to fail on DEC Alpha machines (software below level 3 executes on the DEC Alpha). Updated HEPS calibration parameters have been finalized and are ready for delivery. Updated MEPS quality calibration files have been finalized and are ready for delivery. Level 3 software errors, discovered by Dr. Dean Pesnell, have been fixed; his suggestions have been incorporated with in the PEM production code. Both updated HEPS and MEPS calibration data, along with the Level 3 code changes, will influence the in-situ energy deposition predictions, so new versions of PEM energy deposition Level 3 files will be generated. *Beginning of power orbit day (PEM activation): array current >5 amps, array voltage >53.5 volts, and battery current >2.0 amps. End of power orbit day (PEM deactivation): time in power orbit day >4 minutes, array current <9 amps, and battery currents <0.2 amps. Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta. *********** HALOE *********** Nothing received. *********** MLS *********** Nothing received. *********** HRDI *********** Nothing received. *********** WINDII *********** Nothing received. *********** MPG *********** On 17 July 2001 the MPG participated in the biweeekly three-TDRS meeting. These biweekly meetings are being held to monitor the development of software needed to allow UARS to begin using three TDRS satellites for commanding and data acquistion. Daily processing of instrument Daily Activity Plans continues with no problems. *********** CDHF *********** Nothing received. *********** FOT *********** REPORTING PERIOD This report covers 07 July 2001 (Orbit 53686, GMT Day 188) through 13 July 2001 (Orbit 53790, GMT Day 194). SPACECRAFT OPERATION The observatory is now in Forward Flight (Southern Hemisphere viewing) and is performing nominally under two-battery operations. The instrument operational changes were: INSTRUMENT OPERATIONAL CHANGES Instrument Time Orbit Comment HALOE 194/0047 53776 Power OFF WINDII 194/0643 53780 Power ON The beta angle ranged between the angles of 33.7 degrees to 59.0 degrees for this report period. The beta angle is now increasing towards a maximum angle of 78 degrees on 20 July 2001 (DOY 201). Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 remains OFF the charge relay. Battery 2 and Battery 3 are currently maintaining greater than 23.8 V end-of-night (EON) load bus voltage. Battery temperatures are stable with a temperature delta between Battery 2 and Battery 3 of 1.2 to 1.6 degrees C. Additional battery performance data for each battery on 6 July 2001 and 13 July 2001 are provided in Appendix D. The clock error ranged from Ð11.8 to 10.5 msec during this report period. Clock rate adjustments are listed in Appendix C. All instrument and subsystem engineers were advised on the initial excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for this report. A summary is listed below and the details of ALERT and Out-Of-Limits occurrences are listed in Appendix B. ¥ OUT-OF-LIMITS = 00 ¥ ALERTS = 00 The following real-time command sheets were executed for the listed operational element(s) during this report period (see Appendix A). ¥ FOT = 19 ¥ HALOE = 01 ¥ WINDII = 01 UARS Anomaly Reports initiated during this report period are listed in Appendix E and summarized below. ¥ FOT = 02 One (1) Anomaly Report remained OPEN at the end of this report period (see Appendix E). TRANSPONDER FREQUENCIES: · Transponder A: 00/316 - 2287.496493 · Transponder B: 01/119 - 2287.499116 GROUND SYSTEM OPERATION Two (2) operational support problems occurred this period. Anomaly Reports are included in Appendix E. The data loss calculations supplied by Data Capture Facility (DCF) from mission start through UTC Day 01/193 show the observatory data loss to be 302 hours, 44 minutes, 57.624 seconds. This shows a zero loss since the last report period. This is a 0.39 percent data loss, which equals a 99.61 percent data capture for the mission. OTHER SIGNIFICANT EVENTS UARS SATELLITE OPERATIONS An instrument anomaly was experienced on 05 May 2001. The instrument involved was the ACRIM II instrument. All ACRIM telemetry for currents and voltages all dropped to zero values suddenly. The ACRIM team in coordination with the UARSFOT conducted analysis and command tests to determine the cause of the anomaly. Analysis shows that the anomaly was caused by failed circuitry in the ACRIM electronics box. The FOT is awaiting a future plan of action from the ACRIM team. The software test team, in conjunction with the FOT, has completed a large portion of the testing for the new front end processor. The new TAC still has yet to undergo DSN and realtime TDRS testing, but has completed simulations of receipt of telemetry, commanding, and NCC/GCMR testing. DSN testing is scheduled for 18 July 2001. UARSFOT will also begin supporting testing of the rehosted UARS ground system. A prototype system has been built in accordance with the UARS documentation and operational database. The demo of the prototype system will be held on 02 August 2001 UARS attitude has been adjusted over the course of the last few yaw cycles by loading new alignment matrices for the TAM. Good alignments have been found for both directions of flight and the performance of the TAM should remain stable and accurate. MEETINGS The FOT held the UARS Three TDRS Kickoff Meeting on 03 July 2001. This meeting was established to track the progress and resolve problems of all entities involved in the implementation of the three TDRS mode. This meeting will become a biweekly meeting until the three TDRS mode is operational. FUTURE SIGNIFICANT EVENTS The next UARS Yaw slew is scheduled for 08 August 2001 (DOY 220). This maneuver will be a Forward to Reverse Flight maneuver (Southern Hemisphere viewing). Attachments: Appendix A, Real-time Commands Sheets Appendix B, Out-Of-Limits & ALERT Occurrences Appendix C, Clock & Solar Array Rate Corrections Appendix D, UARS Battery Performance Data Appendix E, UARS Anomaly Reports APPENDIX A REAL-TIME COMMAND SHEETS Week ending 13 July 2001 ORBIT AOS NO. SUBSYS REASON ----- --- --- ------ ------ 53690 188/0740 01-445 NBTR NOOPS D-188 53697 188/1759 01-446 NBTR NOOPS D-189 53704 189/0600 01-446 NBTR NOOPS D-189 53711 189/1650 01-446 NBTR NOOPS D-189 53712 189/1800 01-447 NBTR NOOPS D-190 53719 190/0600 01-447 NBTR NOOPS D-190 53727 190/1801 01-447 NBTR NOOPS D-190 53727 190/1801 01-448 NBTR NOOPS D-191 53729 190/2120 01-449 OBC/CLK Clk Adj 0.0 to 20.6 msec/day 53740 191/1506 01-450 OBC TAM Alignment 53742 191/1801 01-448 NBTR NOOPS D-191 53750 192/0741 01-451 NBTR NOOPS D-192 53753 192/1143 01-451 NBTR PLAYBACK/ /RTS-58 53753 192/1143 01-452 OBC/CLK Clk Adj 20.6 to 0.0 msec/day 53756 192/1620 01-454 TAM TAM ALIGNMENT 53757 192/1802 01-453 NBTR NOOPS D-193 53765 193/0642 01-453 NBTR NOOPS D-453 53776 194/0047 01-455 HALOE Power OFF 53780 194/0643 01-456 WINDII Power ON 53782 194/1005 01-457 OBC Clk Adj 0.0 to 20.6 msec/day 53785 194/1438 01-458 OBC TAM Alignment ______________________________________________________________________________ APPENDIX B OUT-OF-LIMITS & ALERTS OCCURRENCES Week ending 13 July 2001 The following Out-Of-Limits occurrences were detected: MNEMONIC STATE DESCRIPTION ORBITS -------- ----- ----------- ------ -None this report period The following ALERT occurrences were detected: MNEMONIC DESCRIPTION ORBITS -------- ----------- ------ -None this report period _______________________________________________________________________________ APPENDIX C CLOCK & SOLAR ARRAY RATE CORRECTIONS Week ending 13 July 2001 CLOCK DRIFT RATE ADJUSTMENTS ORBIT TIME CLOCK RATE CHANGE ----- ----- ----------------- 53729 190/2128 Clk Adj 0.0 to 20.6 msec/day 53753 192/1150 Clk Adj 20.6 to 0.0 msec/day 53782 194/1008 Clk Adj 0.0 to 20.6 msec/day _______________________________________________________________________________ APPENDIX D UARS BATTERY PERFORMANCE DATA Week ending 13 July 2001 6 July 2001 - GMT Day 187 Beta = 29.3 deg, SA Pos = 269 deg DIFF V (mV) TEMP (C) CURR (amp) EON V AVE C/D AVE BAT MAX/MIN MAX/MIN MAX/MIN MIN RATIO DOD(%) --- ----------- -------- ---------- ------ ------- ------ 1 +728.0/+728.0 -3.05/-4.31 +0.0/+0.0 12.0 0.000 0.0 2 +11.2/-134.4 +5.79/+4.51 +28.4/-14.4 24.8 1.030 20.7 3 +22.4/-56.0 +4.83/+3.23 +28.0/-15.2 24.8 1.020 20.7 13 July 2001 - GMT Day 194 Beta = 59.0 deg, SA Pos = 269 deg DIFF V (mV) TEMP (C) CURR (amp) EON V AVE C/D AVE BAT MAX/MIN MAX/MIN MAX/MIN MIN RATIO DOD(%) --- ----------- -------- ---------- ------ ------- ------ 1 +728.0/+728.0 -3.68/-4.94 +0.0/+0.0 12.0 0.000 0.0 2 +11.2/-33.6 +3.87/+2.60 +22.4/-14.4 26.4 1.030 18.5 3 +22.4/-22.4 +2.92/+1.66 +21.6/-14.4 26.4 1.020 18.0 V/T LEVEL CHANGES ORB# TIME LVL FR-TO ----- ---- --------- -no changes V/T 5 _______________________________________________________________________________ APPENDIX E UARS ANOMALY REPORTS Week ending 13 July 2001 NEW ANOMALY REPORTS GENERATED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 01-042 FOT 53697 188/1759Z N/A Data dropouts/NISN router switch 01-043 FOT 53722 190/0920Z 23951 6 Second TLM dropout at WS ANOMALY CLOSURE INFORMATION RECEIVED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 01-042 FOT 53697 188/1759Z N/A Data dropouts/NISN router switch 01-043 FOT 53722 190/0920Z 23951 6 Second TLM dropout at WS ANOMALY INVESTIGATION REPORTS GENERATED AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- -None this report period OPEN ANOMALY REPORTS AR NO. SUBSYS ORBIT TIME TTR PROBLEM/DATA LOSS ------ ------ ----- ---- --- ----------------- 01-041 FOT see list July 01 14170 Generic Late Acquisition SEVNTFW01/28