UARS Weekly Status Report

12 June 1998




********************************************************************

                UARS WEEKLY STATUS REPORT - 12 JUNE 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE persists with its customary operating status, continuing to amass
celestial statistics during all obtainable solar observation intervals and
astral calibration analyses, whenever feasible.

***********
SUSIM
***********

SUSIM has successfully gathered its normal solar, offset, lamp, and
occultation scan data without apparent problems.

Work is nearly finished on version 7 of the SUSIM production software.

***********
PEM
***********

PEM was not active.

GSFC has proposed an OBC operation plan for the activation of PEM boom 
instruments during the daylight portions of every orbit.  This OBC operation 
plan is accepted by PEM.  PEM has proposed a series of test procedures for 
activation and is waiting response from GSFC.  PEM is also waiting for GSFC
scheduling and implementation of the OBC plan and its operation test procedures.

***********
HALOE 
***********
  
HALOE continues successful operations during this operational period.
HALOE will be powered off at end-of-day today for the upcoming yaw
maneuver.  All engineering parameters are nominal and the science data
results are excellent.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

HRDI is currently off.  Observations from May 31 to June 10 were normal.

***********
WINDII
***********

Nothing received.

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues 
with no other problems.  The MPG continues to assist the Project 
Scientist with the scheduling of instrument operations.

An orbit-adjust maneuver for the UARS spacecraft is being planned 
for 12 August 1998.  In preparation for the thruster firing on 
12 August, small thruster "burns" for calibration are being 
planned for 28 July 1998.

***********
CDHF
***********

The CDHF began receiving orbit data on a daily basis on 06/03/98.
This is a change from the old schedule of receiving this data
on Mon - Wed - Fri.

The CDHF has received a total of 393 CD-ROM requests as of 12-June-1998.
There were three orders received and shipped.
                                        
The CDHF processed current day data through level 3 for all active
instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.
                  26 days PEM (3.32) PROD        (1379R-1339C=40L)
                  81 days HAL (4.80) PROD (L1)   (1868R-392C-2F=1474L)
                  30 days HAL (4.80) PROD (L3)   (1868R-105C=1763L)
                 309 days SOL (4.61) PROD (L1)   (2404R-1463C=941L)
                  76 days SOL (4.61) PROD (L2-L3)(2304R-245C=2059L)  
                 
The CDHF will load April 1998 current day DAAC data in June 1998.
                     
CDHF pending software upgrades: IDL 5.1, OpenIngre

***********
FOT
***********

REPORTING PERIOD

This report covers 30 May 1998 (Orbit 36693, GMT Day 150) through 05 June 
1998 (Orbit 36797, GMT Day 156).


SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing)
and is performing nominally under two-battery operations.  The instrument 
operational changes were:

                INSTRUMENT OPERATIONAL CHANGES

     Instrument     Time       Orbit      Comment
      HRDI        151/0135     36709      On
      MLS         152/2330     36737      Off
     HALOE        153/0107     36738      On

A summary of Instrument operations supplied by the Mission Planning Group 
for the month of May 1998 is contained in Appendix F, UARS Instrument 
Operations Summary.

The beta angle is now decreasing toward a minimum angle of 0.0 degrees on 
15 June 1998 (DOY 166).

Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 25.4 V end-of-night (EON) load bus voltage. 
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 1.1 degrees C.  Additional battery performance data for 
each battery on 30 May 1998 and 05 June 1998 are provided in Appendix D.

The clock error ranged from -10.9 to +9.1 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

%     ALERTS        =   none
%     OUT-OF-LIMITS =   02

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     01
%     HRDI    02
%     MLS     01
%     HALOE   01
%     SUSIM   01

UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     03

One (1) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
     Transponder A:  98/146  -  2287.496748
     Transponder B:  98/147  -  2287.499000


GROUND SYSTEM OPERATION

One (1) operational support problem(s) occurred this period.  Anomaly 
Reports are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/155 show the observatory data loss to be 
20 hours, 43 minutes, 36.628 seconds (an increase of 6.976 seconds since 
last report period).  This is a 0.0353 percent data loss which equals a 
99.9647 percent data capture for the mission.


The increase of 6.976 seconds occurred over a five day period:

7 0.512 seconds on Day 151 due to a hit in data,
7 0.384 seconds on Day 152 due to hits in data,
7 3.072 seconds on Day 153 due to hits in data,
7 2.016 seconds on Day 154 due to hits in data and line errors, and
7 0.992 seconds on Day 155 due to insufficient overlap.

The FOT made a few more modifications to the OBCSTF resident POCC database 
this week.  The latest RtestS version of Database 67 was generated this 
week.  The resulting database tape was given to the MSOCC software 
coordinator, who subsequently installed the database onto the PE41 disk 
pack.  Database testing was performed using PE41, and no problems with the 
database have been discovered to date.

The FOT built three HALOE RTS loads this week as requested by HALOE 
operations to accommodate the HALOE instrument turn-on procedure.  The 
three RTS loads were thought (by HALOE operations) to already be available 
for use, but as it turned out, the loads were sufficiently old and were 
deleted from the CMS system via normal file maintenance.

New versions of RTSs 29 and 30 were generated this week.  The purpose of 
the RTSs is to accommodate testing of the UARS propulsion module (PM) in 
preparation for the UARS orbit adjust maneuver later this year.

Testing the command side of the I/P Net remains on hold.  Testing will 
begin when MSOCC provides a command loop interface from the POCC through 
the I/P Net to the UARS Simulator.


OTHER SIGNIFICANT EVENTS

Continued testing of the upgrade to the OBC Power Monitor (PMON) flight 
software.  PMON software testing continued this week.  Multiple simulations 
on the new AP software were conducted.  However, in the course of testing, 
several problems arose with the ground system software test packs.  These 
problems will be discussed with the programmer and hopefully corrected next 
week.

Completed development and testing of the PMON update uplink procedure to 
load the new PMON flight software.  The procedure was successfully tested.

Work continues on the UARS orbit adjust planning re-scheduled for 12 August 
1998.  FOT was tasked to developed a command sheet and STOL procedure to 
refill the B/D thruster lines.  These were delivered to the customer on 
Thursday afternoon following the 04 June 1998 meeting, and are pending 
approval at the scheduled 09 June 1998 follow-up meeting.

The line refill procedure was tested with the simulator on 06 June 1998.  
Minor adjustments to the UTTS were required to complete the simulation.  
The procedure was successfully tested.

FOT continues to support CNMOS in their efforts to make necessary software 
changes (MSOCC, CMS, DCF, etc.) to support the year 2000 rollover.

Monitoring of the magnetic field model performance continues.

FOT continues to improve a Power Profile for UARS based on the current 
status of the Modular Power System.

FOT continues to support the new UARS ground system re-engineering effort.


MEETINGS

A meeting to discuss the planned orbit adjust was held on 04 June 1998.  
The following points of interest came out of the meeting:

The B/D attitude thrusters will be used, and hence the B/D fuel lines 
will be refilled by an FOT-defined procedure.  The procedure will be 
reviewed by Code 570 at a meeting scheduled for 2:00 p.m. on 09 June 
1998.  The date for refilling the lines will be set at this meeting.

The B/D attitude and translation will be tested on 28 July 1998.  The 
thruster firings will be of very short duration, and will be analyzed 
post-pass by FOT and FDF to determine if performance of the PM is nominal 
for the fairly long-duration orbit adjust to follow.

The orbit adjust is now scheduled for 12 August 1998.

The representatives for the Lockheed Martin Spacecraft Control System - 21 
(SCS-21) were at GSFC from 01 June through 05 June 1998 to discuss the UARS 
functional requirements for a ground support system.  The SCS-21 system is 
being considered as a COTS upgrade system for the UARS command and 
telemetry system.  Meeting were conducted all week to discuss the 
requirements in detail and to assess the SCS-21 current generic 
capabilities and any special implementations required for UARS support.

No UARS Battery telecon was held this week.  The next telecon has not been 
scheduled.


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is currently scheduled for 15 June 1998.

The UARS orbit altitude is dropping slowly and a drag makeup orbit adjust 
is targeted for 05 August 1998.


PERSONNEL CHANGES

None


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports
              Appendix F,  UARS Instrument Operations Summary




                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 05 June 1998

ORBIT        AOS       NO.     SUBSYS    REASON
-----        ---       ---     ------    -------  
36709     151/0135   98-185   HRDI    HRDI ON: HI Power
36732     152/1531   98-186   HRDI    Microload
36737     152/2330   98-187   MLS     Power OFF
36738     153/0107   98-188   HALOE   Power ON
36765     154/2036   98-189   SUSIM   Reloaded Microload
36771     155/0528   98-190   OBC     Clk Adj fr 20.6 to 0.00 msec/day




_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 05 June 1998

MNEMONIC          STATE      DESCRIPTION                       ORBITS
---------         -----      ------------                      ------
WIEUTEMP          Y-LO     WINDII EU Temperature            36788-97
NBBTAPEPOS        R-LO     NBTR B TAPE POSITION             36788


The following ALERT occurrences were detected:

MNEMONIC              DESCRIPTION                           ORBITS
---------             ------------                          ------
          None this report period
          



                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 05 June 1998

                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT             TIME                 CLOCK RATE CHANGE
     -----             ----                 -----------------
     36771     155/05:33 (04 Jun 98)     from 20.6 to 00.0 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 05 June 1998

     30 May 1998 - GMT Day 150 Beta = 67.5 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-4.62   +0.0/ +0.0   18.2   0.000      0.0
2   +22.4/ -11.2  +3.87/+2.60  +21.2/-15.2   26.7   1.034     18.0
3   +84.0/  -5.6  +2.60/+1.66  +20.4/-15.2   26.7   1.031     17.5

     05 Jun 1998 - GMT Day 156 Beta = 43.0 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-4.62   +0.0/ +0.0   18.2   0.000      0.0
2   +22.4/ -22.4  +5.47/+4.51  +28.4/-16.0   25.4   1.024     21.6
3   +84.0/ -11.2  +4.51/+3.23  +27.2/-15.2   25.4   1.028     21.0


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 05 June 1998


                    NEW ANOMALY REPORTS GENERATED
  AR NO.   SUBSYS  ORBIT       TIME       TTR      PROBLEM/DATA LOSS
  ------   ------  -----       ----       ---      -----------------
98-027    FOT     36698     150/0819     N/A     TAC #4 Crashed
98-028    FOT     36746     153/1307     14170   Generic Late Acquisition
98-029    SUSIM   36766     154/2036     N/A     Incorrect Microload


                ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO.   SUBSYS       ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------   ------       -----      ----       ---      -----------------
          None this report period


               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS       ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  -------  ------       -----      ----       ---      -----------------
          None this report period


                      OPEN ANOMALY REPORTS
  AR NO.   SUBSYS       ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  ------   ------       -----      ----       ---      -----------------
98-021     Generic Late Acq for May 1998 (Open until 31 May 1998).
98-026     FOT     36680     149/0312     n/a     TAC Crash
98-027     FOT     36698     150/0819     n/a     TAC Crash
98-028     Generic Late Acq for June 1998 (Open until 30 June 1998).
98-029     SUSIM   36765     154/2036     n/a     Incorrect micro load



_______________________________________________________________
                               APPENDIX F
                   UARS INSTRUMENT OPERATIONS SUMMARY
                      Week ending 05 June 1998


              INSTRUMENT SUMMARY FOR MONTH OF May 1998 (hours)


                                    UNPLANNED      UNSCHEDULED
                 ON        OFF         OFF             OFF     
                                   (Insufficient   (Other than
Instrument  (Actual) (Scheduled)       Power)   Power Problem)  COMMENTS
----------  ------  ----------- -----------    ------------- ------------

ACRIM         744       0             0               0

HALOE         254       490           0               0

HRDI          022       722           0               0

MLS           335       409           0               0

PEM (axis)    197       338           209             0         Note 1

PEM (zeps)    116       628           0               0

PEM (neps)    0         744           0               0

SOLSTICE      744       0             0               0

SUSIM         744       0             0               0

WINDII        295       264           185             0        Note 1

Note 1 - Autonomous turn-off due to power balance


Cold side of spacecraft was facing northward:   4.5 days
Cold side of spacecraft was facing southward:  26.5 days



	 	SEVNTFW23