UARS Weekly Status Report

29 May 1998





********************************************************************

                UARS WEEKLY STATUS REPORT - 29 MAY 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, collecting solar data on all 
available orbital tracking periods and stellar calibration observations, 
whenever possible.  

***********
SUSIM
***********

SUSIM has successfully gathered its normal solar, offset, and
occultation scan data without apparent problems.

***********
PEM
***********

Nothing received.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

MLS was reactivated successfully on May 20, in the reduced 85 watt power mode.
MLS instrument operations have continued flawlessly.  MLS is scheduled to
operate through June 1.

***********
HRDI
***********

HRDI is currently off.  Next scheduled turn-on is May 31st.

***********
WINDII
***********

WINDII WEEKLY REPORT FOR THE WEEK ENDING MAY 29, 1998

WINDII was turned on briefly on May 24, but was then turned off for
lack of power. 

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues 
with no other problems.  The MPG continues to assist the Project 
Scientist with the scheduling of instrument operations.

***********
CDHF
***********

The CDHF and UCSS developer successfully completed the UCSS 10.0 and MSS 4.0
software installation.
 
The CDHF has received a total of 388 CD-ROM requests as of 29-May-1998.
Two orders were received and shipped.

The CDHF is successfully utilizing the new version of the CSC scheduler
Enhancement (New Expansion Tool) in the Solstice v4.61 processing streams.

The CDHF conducted a survey to determine the usage of the UOAS v4.71
UCSS/UOAS Interactive Services Input/Output screen.  The survey was
conducted in regards to PR 2590. Thanks to all for the quick response.

UKMO is experiencing difficulty in transmitting data.  They are currently
working on the problem.        
     
The CDHF processed current day data through level 3 for all active
   instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
   (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.           
                  25 days PEM (3.32) PROD        (1379R-1288C=91L)
                  60 days HAL (4.80) PROD (L1)   (1868R-250C-2F=1616L)
                  43 days HAL (4.80) PROD (L3)   (1868R-44C=1824L)
                 543 days SOL (4.61) PROD (L1)   (2377R-543C=1834L)
                  76 days SOL (4.61) PROD (L3)   (2304R-76C=2228L)
                   1 day  SOL (4.61) PROD (TEST) (1R-1C=0L)
                   1 day  SUS (6.3)  PROD        (1R-1C=0L) 
        
The CDHF received a request from FDF to begin receiving orbit data on a daily
schedule with a two day time lag. Monday Orbit would be received on Wednesday..
Tuesday Orbit on Thursday etc.  We asked that this schedule be put on hold
until all parties involved are notified and in agreement.

CDHF pending software upgrades: IDL 5.1, OpenIngres.                           
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 16 May 1998 (Orbit 36484, GMT Day 136) through 22 May 
1998 (Orbit 36587, GMT Day 142).


SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) 
and is performing nominally under two-battery operations.  The instrument 
operational changes were:

     INSTRUMENT OPERATIONAL CHANGES

     Instrument     Time       Orbit     Comment
     HALOE        139/1719     36539     Off
     MLS          140/0338     36545     On
     PEM          140/2224     36557     ZEPS Off
     PEM          141/0204     36559     ZEPS On

The beta angle reached a minimum angle of 0.0 degrees on 05 May 1998 
(DOY 125).  The beta angle is now increasing toward a maximum angle of 78.0 
degrees on 26 May 1998 (DOY 146).  Spacecraft full-sun (i.e., no Earth 
eclipse) entry began on 21 May 1998 (DOY 141) and will continue until 31 
May 1998 (DOY 151).

Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 
1 remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 24.8 V end-of-night (EON) load bus voltage. 
Battery temperatures are falling (due to high beta angle and low depth-
of-discharge) with a temperature delta between Battery 2 and Battery 3 of 
0.8 degrees C.  Additional battery performance data for each battery on 16 
May 1998 and 22 May 1998 are provided in Appendix D.


The clock error ranged from -9.5 to +12.1 msec during this report 
period.  Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and 
Out-Of-Limits occurrences are listed in Appendix B.

%     ALERTS         =     none
%     OUT-OF-LIMITS  =     none

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     04
%     HALOE   01
%     MLS     01
%     PEM     02

UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     03

One (1) Anomaly Report remained OPEN at the end of this report period 
(see Appendix E).

TRANSPONDER FREQUENCIES:
     Transponder A:  98/118  -  2287.497007
     Transponder B:  98/120  -  2287.498907


GROUND SYSTEM OPERATION

Two (2) operational support problem(s) occurred this period.  Anomaly 
Reports are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/134 show the observatory data loss to 
be 20 hours, 43 minutes, 22.452 seconds (an increase of 11.296 seconds 
since last report period).  This is a 0.0356 percent data loss which equals a 
99.9644 percent data capture for the mission.

The increase of 11.296 seconds occurred over a two day period:

7 1.664 seconds on Day 131 due to hits in the data, and
7 9.632 seconds on Day 132 due to hits in the data and insufficient 
overlap.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/141 show the observatory data loss to 
be 20 hours, 43 minutes, 29.652 seconds (an increase of 07.200 seconds 
since last report period).  This is a 0.0355 percent data loss which equals a 
99.9645 percent data capture for the mission.

The increase of 07.200 seconds occurred over a four day period:

7 1.056 seconds on Day 137 due to hits in the data,
7 0.448 seconds on Day 138 due to hits on line,
7 0.512 seconds on Day 140 due to hits in the data, and
7 5.184 seconds on Day 141 due to hits in the data and on line.

FDF reverted back to a daily ephemeris generation and delivery schedule 
on 21 May 1998 due to the increasing solar flux.  FDF was no longer able to 
meet the allowable ephemeris transition tolerance requirement by 
generating 
ephemeris on a Monday/Wednesday/Friday schedule.

The FOT made a few more modifications to the OBCSTF resident POCC 
database this week.  These changes were supposed to be the last necessary to 
iron out all of the "kinks" in the Database 67 release.  However, late this 
week, HRDI operations (Dave Gell) expressed interest in operating the 
HRDI instrument during spacecraft daylight period only.  This new scenario 
will require a few additional database modifications.  These changes most 
likely will be finalized early next week.

UARS completed testing of the 32 kbps Q-channel dumps using the IP net 
on 14 May 1998. These tests were performed in parallel with the real-time 
operational (NASCOM) system using operational spacecraft data and the 
results were mirrored on both systems.  However, commanding was 
performed only with the real-time system.  All 32 kbps dump types were tested - 
Ephemeris (system table 33 & 34), Absolute Time Commands (ATC), and OBC 
bank dumps.  Dump compares were executed automatically by the 
Applications Processor (AP) with no errors indicated.

Testing the command side of the I/P Net is on hold.  Testing will begin 
when MSOCC provides a command loop interface from the POCC through the 
I/P Net to the UARS Simulator.


OTHER SIGNIFICANT EVENTS

Continued testing of the upgrade to the OBC Power Monitor (PMON) flight 
software.  Minor changes to both the flight software and supporting 
ground database were made during the week.  PMON software modifications and 
testing continued.  Multiple simulation runs to verify integrity of the 
latest modifications, database consistency with the new software, and 
testing of new features were executed.

Work continues on the UARS orbit adjust planning scheduled for 05 August 
1998.  Additional options for an Orbit Adjust are being planned in the 
event that the B/D thrusters can not be safely used.  Data from the 
original anomaly during which the hydrazine lines for the B and D 
attitude thrusters were depleted is being prepared for delivery to the 
Propulsion Branch (Dennis Asata).  The Propulsion Branch stated that they 
cannot supply the latch valve driving circuits and that they must be supplied 
by some other source to complete the latch valve tests.

UARS continues to assisted TOMS in reviewing the TOMS/EP Transmitter A 
failure data.

FOT continues to support CNMOS in their efforts to make necessary 
software changes (MSOCC, CMS, DCF, etc.) to support the year 2000 rollover.

Monitoring of the magnetic field model performance continues.

FOT continues to improve a Power Profile for UARS based on the current 
status of the Modular Power System.

FOT continues to support the new UARS ground system re-engineering 
effort.


MEETINGS

No UARS Battery telecon was held this week.  The next telecon has not 
been scheduled.


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is currently scheduled for 16 June 
1998.

The UARS orbit altitude is dropping slowly and a drag makeup orbit 
adjust is targeted for 05 August 1998.


PERSONNEL CHANGES

Dimitrios Mantziaras, On-Line Evaluation Engineer transferred to an Off-
Line Engineering position effective 13 May 1998.


Attachments:  Appendix A,   Real-time Commands Sheets
              Appendix B,   Out-Of-Limits & ALERT Occurrences
              Appendix C,   Clock & Solar Array Rate Corrections
              Appendix D,   UARS Battery Performance Data
              Appendix E,   UARS Anomaly Reports




                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 22 May 1998

ORBIT    AOS           NO.    SUBSYS      REASON
-----    ---           ---    ------    -------  
36503     137/0922   98-168   OBC     Clk Adj fr 20.6 to 0.00 msec/day
36526     138/2040   98-169   OBC     Clk Adj fr 0.00 to 20.6 msec/day
36539     139/1719   98-170   HALOE   Power OFF
36545     140/0338   98-171   MLS     Power ON
36557     140/2224   98-172   PEM     Power OFF ZEPS
36559     141/0204   98-173   PEM     Power ON AXIS
36569     141/1735   98-174   OBC     Clk Adj fr 20.6 to 41.2 msec/day
36585     142/1920   98-175   OBC     Reload RTs 12




_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 22 May 1998

MNEMONIC           STATE     DESCRIPTION                ORBITS
---------          -----    ------------                ------
          None this report period


The following ALERT occurrences were detected:

MNEMONIC                   DESCRIPTION                 ORBITS
---------                  ------------                ------
          None this report period
          



                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 22 May 1998

                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                  CLOCK RATE CHANGE
     -----              ----                   -----------------
     36503     137/09:29 (17 May 98)     from 20.6 to 00.0 msec/day
     36526     138/20:44 (18 May 98)     from 00.0 to 20.6 msec/day
     36569     141/17:35 (21 May 98)     from 20.6 to 41.2 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 22 May 1998

     16 May 1998 - GMT Day 136 Beta = 45.0 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V  AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN    RATIO   DOD(%)
---  ------------  ---------- -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-4.62   +0.0/ +0.0   18.2   0.000    0.0
2   +33.6/ -22.4  +6.11/+4.51  +28.4/-16.0   24.8   1.020   22.3
3   +67.2/  -5.6  +5.15/+3.23  +27.2/-16.8   24.8   1.022   21.8

     22 May 1998 - GMT Day 142 Beta = 69.5 deg, SA Pos = 269 deg

      DIFF V (mV)   TEMP (C)    CURR (amp)   EON V  AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN    RATIO   DOD(%)
---  ------------  ---------- -----------  -------  -------  ------
1  +728.0/+728.0  -3.68/-4.94   +0.0/ +0.0   18.4   0.000    0.0
2   +44.8/ -11.2  +3.87/+2.29  +20.0/-16.4   24.8   1.004   18.6
3   +67.2/  +0.0  +2.92/+1.34  +19.2/-16.4   24.8   1.012   18.1


     V/T LEVEL CHANGES
ORB#   TIME          LVL FR-TO
-----  --------      ----------
          no changes



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 22 May 1998


                  NEW ANOMALY REPORTS GENERATED
  AR NO.    SUBSYS ORBIT    TIME     TTR      PROBLEM/DATA LOSS
  ------    ------ -----    ----     ---      -----------------
98-021     FOT    36509  137/1724  14170    Generic Late Acquisition
98-021     FOT    36514  138/0141  14170    Generic Late Acquisition
98-024     FOT    36572  141/2323  N/A      TAC Crashed


             ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO. SUBSYS   ORBIT   TIME       TTR     PROBLEM/DATA LOSS
  ------ ------  -----   ----        ---     -----------------
98-024     FOT  36572  141/23:27           TAC 4 CRASH


               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS    ORBIT      TIME       TTR   PROBLEM/DATA LOSS
  -------  ------    -----      ----       ---   -----------------
          None this report period


                       OPEN ANOMALY REPORTS
  AR NO.   SUBSYS     ORBIT     TIME      TTR   PROBLEM/DATA LOSS
  ------   ------    -----     ----       ---   -----------------
98-021    Generic Late Acq for May 1998 (Open until 31 May 1998).


           SEVNTFW21