UARS Weekly Status Report

20 April 2001




********************************************************************

                UARS WEEKLY STATUS REPORT - 20 APR 2001

********************************************************************

***********
SOLSTICE
***********

SOLSTICE began day only operations on day 109 this week in support of the
yaw maneuver. We'll be returning to normal operations at the beginning of
day 112. Otherwise, SOLSTICE continues to operate normally, taking solar
data on all available orbital tracking periods and stellar calibration
observations whenever possible. We continue to gather enough data to meet
all the SOLSTICE science objectives during this period of reduced tape 
recorder operations.

***********
SUSIM
***********

Nothing received.

***********
ACRIM
***********

Nothing received.

***********
PEM
***********

     PEM/AXIS was activated in its full power mode on April 1 and deactivated
on April 9.  At the current time, AXIS is not generating energy deposition.  
SwRI is looking into this.  Tests of AXIS production code on the rehost 
computer are continuing.

     At the present time, PEM energy deposition from its spectrometers is not 
being generated.  Recent data configuration changes have affected PEM software 
causing multiple failures.  These failures are being reviewed by the PEM team.
In order to correct for new telemetry requirements, PEM will need to update 
processing code with a patch delivery.  The delivery patch may include changes 
which would allow the PEM software to execute on a DEC Alpha machine.  GSFC is
helping PEM with some DEC Alpha particulars which have caused PEM level 3
code to fail on DEC Alpha machines (software below level 3 executes on the
DEC Alpha).

     PEM has examined its processed files of the rehost machine and has found 
that no differences exist in the Level 1 and Level 2 output files which were 
generated the rehost when the same input data was used on CDHF and CDHFB.
PEM is now confident that output generated by PEM 3.32, Jobs 1 & 2, on the 
rehost system is valid and correct.

     The PEM team is working on replacing the PEM:: machine with a DEC Alpha 
machine to be called PEM2K::.  Tests of the NRT data transfer from CDHF2:: 
through PEM2K:: to the unix computer running the PEM GSE software show no 
difference between equivalent NRT files transferred from PEM::.  Thus, NRT 
data from CDHF2:: is captured correctly on PEM2K::.  Tests of the NRT data 
transfer from CDHFB:: were not successful from both PEM:: and PEM2K::.  
Results of the test of NRT data transfers from the rehost computer were
successful for individual files which exist on CDHFB::.  PEM will participate
in the NRT data flow to capture NRT data from CDHFB:: when specified by GSFC.

     PEM has been working with GSFC on allowing commanding of the PEM
instrument by creating DAPs on the PEM2K machine and submitting them to the 
CMS.  So far, this has not been achieved.  It was discovered that PEM2K is 
running Openwindows version 7.2-1 which operates differently across the 
network than Openwindows version 7.1-2 (the CDHFB operating system).  Compaq 
is investigating to determine a solution.  In the mean time, Steve Bove made
some suggestions which seem to have improved the PEM2K:: to UCMS:: image
execution ability; however, the CMS has had troubles recently and it appears
that the UCMS:: definitions for PEM2K:: must not be correct on the UCMS:: node.
PEM is waiting on a reply back from GSFC.

    Updated HEPS calibration parameters have been finalized and are ready for 
delivery.  Updated MEPS quality calibration files have been finalized and are 
ready for delivery.  Level 3 software errors, discovered by Dr. Dean Pesnell, 
have been fixed; his suggestions have been incorporated with in the PEM 
production code.  Both updated HEPS and MEPS calibration data, along with the 
Level 3 code changes, will influence the in-situ energy deposition predictions,
so new versions of PEM energy deposition Level 3 files will be generated.

*Beginning of power orbit day (PEM activation): array current >5 amps, array 
     voltage >53.5 volts, and battery current >2.0 amps.  
 End of power orbit day (PEM deactivation): time in power orbit day >4 minutes,
     array current <9 amps, and battery currents <0.2 amps.
 Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

Nothing received.

***********
WINDII
***********

Nothing received.

***********
MPG
***********

Daily processing of instrument Daily Activity Plans continues
with no problems. Instrument operations schedule is now complete
to 30 May 2001.

***********
CDHF
***********

 CURRENT SYSTEM
---------------
The CDHF and CDHF REHOST will be unavailable from April 22 9:30 GMT until 
power up time at 11:30 GMT (tentative) April 23. This is due to a scheduled
building power outage. 
This information is contained in the Login Notice as well as a telephone outage
schedule.

CLAES has requested Version 7 (Output 9) excluding Subtypes 3AL, 3AT (H20,
NO2B7, NU3VT626, O3B7, O3B8, ALT) are to be transferred to the DAAC.
Plans are to start previewing and loading data into the DAAC Transfer
Tables.
 
Data created in the month of February 2001 has been previewed for HALOE,
NMC, and UKMO in preparation for sending to the DAAC.

 UARS CDHF REHOST
-----------------
Validating a mandatory upgrade of the HSM. This is the software that "Puts" 
and Gets" data from the Silo. 
                  
***********
FOT
***********

                          REPORTING PERIOD

This report covers 07 April 2001 (Orbit 52321, GMT Day 097) through 13 April 
2001 (Orbit 52425, GMT Day 103).
   
                         SPACECRAFT OPERATION

The observatory is now in Reverse Flight (Northern Hemisphere viewing) and is 
performing nominally under two-battery operations.  The instrument operational 
changes were:


                   INSTRUMENT OPERATIONAL CHANGES


   Instrument     Time     Orbit     Comment          
    PEM           100/2345   52365     Power OFF AXIS          

The beta angle ranged between the angles of -45.9 degrees to -27.8 degrees for 
this report period.  The beta angle is now increasing towards a maximum angle 
of +74 degrees on 09 May 2001 (DOY 129).

Spacecraft battery 1, 2, and 3 performance monitoring continues.  Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  Battery 
temperatures are stable with a temperature delta between Battery 2 and Battery 
3 of 1.3 and 1.6 degrees C.  Additional battery performance data for each 
battery on 06 April 2001 and 13 April 2001 are provided in Appendix D.

The clock error ranged from ~11.6 to 9.4 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial excursion of 
ALERTS or Out-Of-Limits conditions detected by the FOT for this report.  A 
summary is listed below and the details of ALERT and Out-Of-Limits occurrences 
are listed in Appendix B.
¥     OUT-OF-LIMITS  =  00
¥     ALERTS         =  00

The following real-time command sheets were executed for the listed operational 
element(s) during this report period (see Appendix A).

¥     FOT            =  19
¥     PEM/AXIS       =  01


UARS Anomaly Reports initiated during this report period are listed in Appendix 
E and summarized below.

¥     FOT            =  03

One (1) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
· Transponder A:  00/316  - 2287.496493
· Transponder B:  01/087  - 2287.499152


                       GROUND SYSTEM OPERATION

Three (3) operational support problems occurred this period.  Anomaly Reports 
are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from mission 
start through UTC Day 01/067 show the observatory data loss to be 300 hours, 1 
minute, 12.760 seconds. This shows no change since the last report period. This 
is a 0.39 percent data loss, which equals a 99.61 percent data capture for the 
mission.

                      OTHER SIGNIFICANT EVENTS

                      UARS SATELLITE OPERATIONS

UARS is using both the Fine Sun Sensor (FSS) and the Three Axis Magnetometer 
(TAM) as inputs to UFLTR this week.  The FOT is pleased with their performance, 
but continues to make adjustments to the TAM alignment to improve its 
performance and UARS's attitude.

The FOT awaits the completion of the FSW patch that will improve the magnetic 
field model from a 5th order to 7th order solution.  The patch is currently 
being tested on the UARS Testing and Training Simulator (UTTS). Testing should 
be completed in the next few weeks.

                             MEETINGS

There were no meetings during this time period.

                       FUTURE SIGNIFICANT EVENTS
The next UARS Yaw slew is scheduled for 19 April 2001 (DOY 109).  This maneuver 
will be a Reverse to Forward Flight maneuver (Southern Hemisphere viewing).


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports

                           APPENDIX A
                      REAL-TIME COMMAND SHEETS
                     Week ending 13 April 2001

ORBIT     AOS        NO.      SUBSYS     REASON
-----     ---        ---      ------     ------
52325     097/0819   01-217   NBTR       NOOPS D-097
52331     097/1757   01-218   NBTR       NOOPS D-098
52334     097/2156   01-219   OBC        Clk Adj 20.6 to 0.00 msec/day
52340     098/0736   01-218   NBTR       NOOPS D-098
52346     098/1758   01-220   NBTR       NOOPS D-099
52355     099/0737   01-220   NBTR       NOOPS D-099
52360     099/1521   01-221   TAM        TAM Alignment
52361     099/1702   01-222   TAM        MAGMOD Update
52362     099/1759   01-223   NBTR       NOOPS D-100
52365     100/2345   01-224   PEM        Power OFF AXIS
52369     100/0642   01-223   NBTR       NOOPS D-100
52377     100/1800   01-225   NBTR       NOOPS D-101
52385     101/0742   01-225   NBTR       NOOPS D-101
52389     101/1441   01-227   OBC        CMDTST Scheduler Adjust
52392     101/1801   01-228   NBTR       NOOPS D-102
52399     102/0643   01-228   NBTR       NOOPS D-102
52405     102/1621   01-229   OBC        Clk Adj 20.6 to 0.00 msec/day
52407     102/1803   01-230   NBTR       NOOPS D-103
52414     103/0600   01-230   NBTR       NOOPS D-103
52422     103/1804   01-231   NBTR       NOOPS D-104
___________________________________________________________________________

                           APPENDIX B
              OUT-OF-LIMITS & ALERTS OCCURRENCES
                  Week ending 13 April 2001

The following Out-Of-Limits occurrences were detected:

MNEMONIC     STATE     DESCRIPTION     ORBITS
--------     -----     -----------     ------
-None this report period


The following ALERT occurrences were detected:

MNEMONIC     DESCRIPTION     ORBITS
--------     -----------     ------
-None this report period

_______________________________________________________________________________

                           APPENDIX C
             CLOCK & SOLAR ARRAY RATE CORRECTIONS
                   Week ending 13 April 2001

                CLOCK DRIFT RATE ADJUSTMENTS

ORBIT     TIME         CLOCK RATE CHANGE
-----     -----        -----------------
52334     097/2159     Clk Adj 20.6 to 0.00 msec/day
52405     102/1625     Clk Adj 20.6 to 0.00 msec/day     
___________________________________________________________________________

                           APPENDIX D
               UARS BATTERY PERFORMANCE DATA
                 Week ending 13 April 2001


     06 Apr 2001 - GMT Day 096 Beta = 48.1 deg, SA Pos = 269 deg

     DIFF V (mV)    TEMP (C)     CURR (amp)   EON V   AVE C/D   AVE
BAT  MAX/MIN        MAX/MIN      MAX/MIN      MIN     RATIO     DOD(%)
---  -----------    --------     ---------    -----   -------   ------
1    +044.8/+022.4  -3.68/-4.62  +0.0/+0.0    13.0    0.000     0.0
2    +22.4/-44.8    +5.15/+3.87  +26.4/-15.2  25.0    1.050     19.7
3    +22.4/-33.6    +3.87/+2.60  +25.6/-15.2  25.0    1.040     19.5


     13 Apr 2001 - GMT Day 103 Beta = 27.8 deg, SA Pos = 269 deg

     DIFF V (mV)    TEMP (C)      CURR (amp)   EON V    AVE C/D   AVE
BAT  MAX/MIN        MAX/MIN       MAX/MIN      MIN      RATIO     DOD(%)
---  -----------    --------      ---------    ------   -------   ------
1    +067.2/+044.8  -3.05/-4.31   +0.0/+0.0    13.0     0.000     0.0
2    +11.2/-100.8   +6.44/+5.15   +29.6/-15.6  24.0     1.040     21.8
3    +22.4/-67.2    +5.47/+3.87   +28.8/-16.0  23.8     1.030     21.7


     V/T LEVEL CHANGES
ORB#            TIME      LVL FR-TO
----            ----      ---------
-no changes     V/T 5
____________________________________________________________________________

                                APPENDIX E
                      UARS ANOMALY REPORTS
                    Week ending 13 April 2001

                   NEW ANOMALY REPORTS GENERATED
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
01-019     FOT        52363     099/1942   14170   Generic Late Acquisition
01-021     FOT        52383     101/0417   23834   TPF not receiving PBK
01-022     FOT        52398     102/0417   23836   TPF did not get 512k PBK

             ANOMALY CLOSURE INFORMATION RECEIVED
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
01-021     FOT        52383     101/0417   23834   TPF not receiving PBK
01-022     FOT        52398     102/0417   23836   TPF did not get 512k PBK

              ANOMALY INVESTIGATION REPORTS GENERATED
AR NO.     SUBSYS     ORBIT     TIME     TTR       PROBLEM/DATA LOSS
------     ------     -----     ----     ---       -----------------
-None this report period

                     OPEN ANOMALY REPORTS
AR NO.     SUBSYS     ORBIT     TIME     TTR       PROBLEM/DATA LOSS
------     ------     -----     ----     ---       -----------------
01-019     FOT        see list  Apr 01   14170     Generic Late Acquisition



	 	SEVNTFW01/15