UARS Weekly Status Report

23 March 2001




********************************************************************

                UARS WEEKLY STATUS REPORT - 23 March 2001

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, taking solar data on all available
orbital tracking periods and stellar calibration observations whenever
possible. We continue to gather enough data to meet all the SOLSTICE
science objectives during this period of reduced tape recorder operations.

***********
SUSIM
***********

SUSIM performed its daily solar scans this past week during
periods of predicted UARS telemetry.

We have made a request to the Project and fellow SSPP instrument teams
that the SSPP be operated in closed loop tracking mode during our
upcoming major calibration slated for early May.  The improved tracking
would improve the reliability of the calibration.

The calibrations necessary for version 21 of the SUSIM data are complete.
We expect to begin reprocessing when the CDHF rehosting is finished.

***********
ACRIM
***********

The Instrument Science Team continues re-processing ACRIM II data. Target 
date for release of version 2 results is April or May, 2001. The ACRIM II 
instrument is operating normally, obtaining a full set of data each day. 
No significant impact of the SSPP pointing degradation has been detected.

***********
PEM
***********

     PEM/AXIS was activated in its half power mode on March 19 and deactivated
on March 13.  At the current time, AXIS is not generating energy deposition.  
SwRI is looking into this.  Tests of AXIS production code on the rehost computer
seem to indicate that there are system file access violations on the rehost 
computer, which are as yet unexplained.

     At the present time, PEM energy deposition from its spectrometers is not 
being generated.  Recent data configuration changes have affected PEM software 
causing multiple failures.  These failures are being reviewed by the PEM team.
In order to correct for new telemetry requirements, PEM will need to update 
processing code with a patch delivery.  The delivery patch may include changes 
which would allow the PEM software to execute on a DEC Alpha machine.  GSFC is
helping PEM with some DEC Alpha particulars which have caused PEM level 3
code to fail on DEC Alpha machines (software below level 3 executes on the
DEC Alpha).

     PEM has examined its processed files of the rehost machine and has found 
differences between those and the cataloged files in the UARS database.  The 
PEM investigation found that the Level 0 files used to generate the rehost 
data were not the same as those used in previous production.  Therefore, PEM 
finds that the test is not valid and does NOT APPROVE production of PEM data 
on the rehost machine at this time.

     The PEM team is working on replacing the PEM:: machine with a DEC Alpha 
machine to be called PEM2K::.  PEM has requested DAP command capability with 
the CMS from PEM2K::.  Tests of the NRT data transfer from CDHF2:: through
PEM2K:: to the unix computer running the PEM GSE software show no difference
between equivalent NRT files transferred from PEM::.  Thus, NRT data from
CDHF2:: is captured correctly on PEM2K::.  Tests of the NRT data transfer
from CDHFB:: were not successful from both PEM:: and PEM2K::.  Results of the
test of NRT data transfers from the rehost computer acted like the rehost
computer did not recognize either PEM machine.  Investigation is underway.

     PEM has been working with GSFC on allowing commanding of the PEM
instrument by creating DAPs on the PEM2K machine and submitting them to the 
CMS.  So far, this has not been achieved.  It was discovered that PEM2K is 
running Openwindows version 7.2-1 which operates differently across the 
network than Openwindows version 7.1-2 (the CDHFB operating system).  Compaq 
is investigating to determine a solution.

    Updated HEPS calibration parameters have been finalized and are ready for 
delivery.  Updated MEPS quality calibration files have been finalized and are 
ready for delivery.  Level 3 software errors, discovered by Dr. Dean Pesnell, 
have been fixed; his suggestions have been incorporated with in the PEM 
production code.  Both updated HEPS and MEPS calibration data, along with the 
Level 3 code changes, will influence the in-situ energy deposition predictions,
so new versions of PEM energy deposition Level 3 files will be generated.

*Beginning of power orbit day (PEM activation): array current >5 amps, array 
     voltage >53.5 volts, and battery current >2.0 amps.  
 End of power orbit day (PEM deactivation): time in power orbit day >4 minutes,
     array current <9 amps, and battery currents <0.2 amps.
 Power orbit day variation: ~39-40 min at yaw to ~50-51 min at maximum beta.

***********
HALOE 
***********

Nothing received.

***********
MLS
***********

Nothing received.

***********
HRDI
***********

HRDI continues to function normally, making wind measurements during
the sunlit parts of orbits nearly every day, and measuring nighttime winds
when power is available.

***********
WINDII
***********

Nothing received.

***********
MPG
***********
 
Daily processing of instrument Daily Activity Plans continues
with no problems. Instrument operations schedule is now complete
to 19 April 2001.

***********
CDHF
***********

Nothing received.
                  
***********
FOT
***********

                           REPORTING PERIOD

This report covers 10 March 2001 (Orbit 51901, GMT Day 069) through 16 March 
2001 (Orbit 52005, GMT Day 075).

                         SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) and is 
performing nominally under two-battery operations.  The instrument operational 
changes were:


                INSTRUMENT OPERATIONAL CHANGES


     Instrument     Time     Orbit     Comment          
 HALOE        070/2256   51930     Power OFF                    
 PEM          071/2038   51943     Calibration          
 PEM          072/0041   51946     PEM to day only          
 PEM          072/2300   51960     AXIS 1 OFF               
 PEM          073/2302   51975     Power OFF          
 ACRIM        073/2302   51975     Power OFF          
 SUSIM        073/2302   51975     Power OFF          
 SOLSTICE     074/0004   51975     Day only operations          
 HRDI         074/2235   51989     INST PB OFF     


A Forward-to-Reverse Yaw Around maneuver (number 97) was successfully executed 
in Orbit 51984 beginning 074/15:16:52 and completing at 074/15:48:00 on 15 
March 2001.  The SOLSTICE instrument was in day only and all other instruments 
were in their off or standby mode (including HRDI and PEM).  Due to the SA 
position at 269 degrees, the effective night length of the spacecraft after the 
maneuver was approximately 55.4 minutes.  Post maneuver analysis of data 
indicate that during the Yaw Around, the end-of-night load bus voltage was 
24.10 volts and the average depths of discharge (DODs) on Batteries 2 and 3 
were approximately 22.0 and 23.0 percent respectively.  The next (reverse-to-
forward) YAW is scheduled for 19 April 2001 (DOY 109).

The beta angle ranged between the angles of 21.4 degrees to 01.5 degrees for 
this report period.  The beta angle is now decreasing towards a minimum angle 
of 52 degrees on 02 April 2001 (DOY 074).

Spacecraft battery 1, 2, and 3 performance monitoring continues.  Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 23.8 V end-of-night (EON) load bus voltage.  Battery 
temperatures are stable with a temperature delta between Battery 2 and Battery 
3 of 1.2 and 1.3 degrees C.  Additional battery performance data for each 
battery on 09 March 2001 and 16 March 2001 are provided in Appendix D.


The clock error ranged from -10.4 to 11.9 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial excursion of 
ALERTS or Out-Of-Limits conditions detected by the FOT for this report.  A 
summary is listed below and the details of ALERT and Out-Of-Limits occurrences 
are listed in Appendix B.

¥     OUT-OF-LIMITS  =  00
¥     ALERTS         =  00

The following real-time command sheets were executed for the listed operational 
element(s) during this report period (see Appendix A).

¥     FOT            =   11
¥     PEM            =   09



UARS Anomaly Reports initiated during this report period are listed in Appendix 
E and summarized below.

¥     FOT            =  01

One (1) Anomaly Report remained OPEN at the end of this report period (see 
Appendix E).

TRANSPONDER FREQUENCIES:
· Transponder A:  00/316  - 2287.496493
· Transponder B:  02/026  - 2287. 49920005


                     GROUND SYSTEM OPERATION


One (1) operational support problems occurred this period.  Anomaly Reports are 
included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from mission 
start through UTC Day 01/067 show the observatory data loss to be 300 hours, 20 
minutes, 29.464 seconds. This shows an overall increase of 29.616 seconds since 
the last report period. This is a 0.39 percent data loss, which equals a 99.61 
percent data capture for the mission.

The increase of 29.616 seconds occurred over two (2) days:

· 15.072 seconds on Day 071 due to No Data Overlap
· 14.544 seconds on Day 074 due to No Data Overlap

                    OTHER SIGNIFICANT EVENTS


                    UARS SATELLITE OPERATIONS

UARS is using both the Fine Sun Sensor (FSS) and the Three Axis Magnetometer 
(TAM) as inputs to UFLTR this week.  The FOT is pleased with their performance, 
but continues to make adjustments to the TAM alignment to improve its 
performance and UARS' attitude.  The FOT awaits the completion of the FSW patch 
that will improve the magnetic field model from a 5th order to 7th order 
solution.

                            MEETINGS

The FOT attended a TAC Replacement Meeting on Tuesday, March 13, 2001.
The FOT attended a TAC Replacement Meeting on Friday, March 16, 2001


                    FUTURE SIGNIFICANT EVENTS


The next UARS Yaw slew is scheduled for 19 April 2001 (DOY 109).  This maneuver 
will be a Reverse to Forward Flight maneuver (Southern Hemisphere viewing).


Attachments:  Appendix A,  Real-time Commands Sheets
              Appendix B,  Out-Of-Limits & ALERT Occurrences
              Appendix C,  Clock & Solar Array Rate Corrections
              Appendix D,  UARS Battery Performance Data
              Appendix E,  UARS Anomaly Reports

                           APPENDIX A
                    REAL-TIME COMMAND SHEETS
                    Week ending 16 March 2001

ORBIT     AOS          NO.      SUBSYS     REASON
-----     ---          ---      ------     ------
51912     069/1845     01-150   NBTR       NOOPS D070
51920     070/0726     01-150   NBTR       NOOPS D-070
51930     070/2256     01-151   HALOE      Power OFF
51941     071/1741     01-152   OBC        MAGMOD Time Update
51943     071/2038     01-153   PEM        Calibration
51944     071/2114     01-154   ACS        TAM/FSS Monitor/Update Mode
51944     071/2114     01-155   ACS        TAM Alignment
51946     072/0041     01-153   PEM        PEM to day only
51960     072/2300     01-156   PEM        AXIS 1 OFF
51969     073/1423     01-157   OBC        Clk Adj fr 0.0 to -20.6 msec/day
51975     073/2302     01-158   PEM        Power OFF
51975     073/2302     01-159   ACRIM      Power OFF
51975     073/2302     01-160   SUSIM      Power OFF
51975     074/0004     01-161   SOLSTICE   Day only operations
51984     074/1424     01-162   ACS        TAM to MONITOR MODE
51984     074/1424     01-163   ACS        YAW MANEUVER  FWD to REV
51985     074/1619     01-164   ACS        TAM ALIGN/ UPDATE MODE
51987     074/1911     01-166   ACS        TAM GAIN CHANGE
51989     074/2235     01-167   HRDI       INST PB OFF
51986     074/1723     01-165   OBC        Clk Adj fr -20.6 to 0.0 msec/day
_______________________________________________________________________________

                           APPENDIX B
              OUT-OF-LIMITS & ALERTS OCCURRENCES
                  Week ending 16 March 2001

The following Out-Of-Limits occurrences were detected:

MNEMONIC     STATE     DESCRIPTION     ORBITS
--------     -----     -----------     ------
-None this report period


The following ALERT occurrences were detected:

MNEMONIC     DESCRIPTION     ORBITS
--------     -----------     ------
-None this report period     51883

_______________________________________________________________________________

                           APPENDIX C
              CLOCK & SOLAR ARRAY RATE CORRECTIONS
                   Week ending 16 March 2001

                  CLOCK DRIFT RATE ADJUSTMENTS

ORBIT     TIME         CLOCK RATE CHANGE
-----     -----        -----------------
51969     073/1429     Clk Adj fr 0.0 to -20.6 msec/day
51986     074/1734     Clk Adj fr -20.6 to 0.0 msec/day
___________________________________________________________________________

                           APPENDIX D
                 UARS BATTERY PERFORMANCE DATA
                  Week ending 16 March 2001


     09 Mar 2001 - GMT Day 068 Beta = 25.2 deg, SA Pos = 269 deg

     DIFF V (mV)     TEMP (C)     CURR (amp)    EON V     AVE C/D   AVE
BAT  MAX/MIN         MAX/MIN      MAX/MIN       MIN       RATIO     DOD(%)
---  -----------     --------     ---------     ------    -------   -----
1    +016.8/+00.0    -3.05/-4.    +0.0/+0.0     13.0      0.000     0.0
2    +16.8/-89.6     +5.79/+4.51  +30.0/-14.4   24.5      1.030     21.1
3    +22.4/-95.2     +4.51/+3.55  +29.6/-14.4   24.3      1.020     20.9


     16 Mar 2001 - GMT Day 075 Beta = 01.5 deg, SA Pos = 269 deg

     DIFF V (mV)     TEMP (C)      CURR (amp)    EON V    AVE C/D   AVE
BAT  MAX/MIN         MAX/MIN       MAX/MIN       MIN      RATIO     DOD(%)
---  -----------     --------      ---------     ------   -------   -----
1    +022.4/+00.0    -3.68/-4.94   +0.0/+0.0     13.0     0.000     0.0
2    +16.8/-89.6     +5.15/+4.19   +29.6/-13.6   25.3     1.020     20.4
3    +33.6/-44.8     +3.87/+2.92   +28.8/-13.2   25.3     1.020     20.0


     V/T LEVEL CHANGES
ORB#          TIME          LVL FR-TO
----          ----     ---------
-no changes   V/T 5

_______________________________________________________________________________

                                APPENDIX E
                     UARS ANOMALY REPORTS
                   Week ending 16 March 2001

                  NEW ANOMALY REPORTS GENERATED
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
01-014     FOT        51921     070/0909   14170   Generic Late Acquisition

            ANOMALY CLOSURE INFORMATION RECEIVED
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
-None this report period

            ANOMALY INVESTIGATION REPORTS GENERATED
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
-None this report period

                      OPEN ANOMALY REPORTS
AR NO.     SUBSYS     ORBIT     TIME       TTR     PROBLEM/DATA LOSS
------     ------     -----     ----       ---     -----------------
01-014     FOT        see list  Mar 01     14170   Generic Late Acquisition



           SEVNTFW01/11