UARS Weekly Status Report

6 March 1998





********************************************************************

                UARS WEEKLY STATUS REPORT - 06 March 1998

********************************************************************

***********
SOLSTICE
***********

SOLSTICE continues to operate normally, collecting solar data on all 
available orbital tracking periods and stellar calibration observations, 
whenever possible.  

***********
SUSIM
***********

SUSIM successfully gathered its normal solar, offset, and occultation
scan data during this past week without apparent problems.

SUSIM dwelled on the strong Lyman alpha emission line during last
Thursday's solar eclipse which, at maximum, was about 85% of totality.

***********
PEM
***********

     PEM/AXIS was activated March 2 and is now producing energy deposition 
profiles from electrons inverted from the AXIS X-ray measurements.

     PEM is awaiting evaluation by GSFC of its proposed activation procedure.
The minimal configuration for PEM AUX activation is the zenith VMAG, MEPS1, 
MEPS2, and HEPS1 units, only.  This configuration is driven by the capabilities 
of the spacecraft OBC and may increase if OBC program area increases.  PEM 
activation is proposed to be OBC driven when there exists plenty of power to 
operate PEM.  It is anticipated that the OBC will activate PEM on the daylight 
portions of every orbit.

***********
HALOE 
***********

HALOE was powered on March 4, 1998.  All engineering parameters are nominal
and the science channel outputs are within expected values.

***********
MLS
***********

The MLS instrument has been powered off since Mar 3. MLS is scheduled to
resume south viewing operations on Mar 12.

***********
HRDI
***********

HRDI is currently off.  Next expected turn-on is March 7.

***********
WINDII
***********

Nothing received.

***********
MPG
***********

Routine processing of instrument Daily Activity Plans continues
with no problems.  The MPG continues to assist the Project
Scientist with the scheduling of instrument operations.

As part of the UARS re-engineering effort, two CISCO routers 
are being installed with the MPG RAC.  These routers are being 
set up so that the Command Management System and the MPG RAC 
will no longer depend on the routers located in Building 23 
with the UARS CDHF.  

***********
CDHF
***********

The CDHF has received a total of 376 CD-ROM requests as of 06-March-1998.
Four orders were received and shipped.
                          
The CDHF processed current day data through level 3 for all active
instruments. Additionally, CDHF personnel reprocessed: (R)= Requested
  (C) = Complete, (F)= Failed  (L) = Days remaining to reprocess.          
                  25 days PEM (3.32) PROD (1379R-979C=400L)
                 123 days MLS (4.90) PROD (1297R-804C=493L)
                  8 days CLAES (7.0) ENG   (17R-9C=8L)               

The CDHF continues to work with NSI to develop a support plan for the 
entire UARSNET network, focusing on Instrument RACs first, redesign issues, 
and then the global user community. 

The CDHF will load January 1998 current day DAAC data in March 1998.

Pending software upgrades: IDL 5.0, OpenIngres, UCSS. 
                  
***********
FOT
***********

REPORTING PERIOD

This report covers 21 February 1998 (Orbit 35226, GMT Day 052) through 27 
February 1998 (Orbit 35329, GMT Day 058).


SPACECRAFT OPERATION

The observatory is now in Forward Flight (Southern Hemisphere viewing) and 
is performing nominally under two-battery operations.  The instrument 
operational changes were:

         INSTRUMENT OPERATIONAL CHANGES

  Instrument     Time       Orbit     Comment
     MLS       053/2329     35255     Off
   WINDII      057/1027     35307     On
   WINDII      057/2004     35313     Off

The beta angle reached a minimum angle of 0.0 degrees on 25 February 1998 
(DOY 056).  The beta angle is now increasing toward a maximum angle of 54.5 
degrees on 15 March 1998 (DOY 074).

Four (4) SSPP SOLSTICE offsets requested by SUSIM operations were performed 
this week.  One offset took place each day, beginning with GMT Day 052 and 
ending with GMT Day 055.

A Reverse-to-Forward Yaw Around maneuver (number 66) was successfully 
executed in Orbit 35294 at 14:35:50 UTC on 25 February 1998.  The SSPP 
Instruments (ACRIM, SOLSTICE, and SUSIM) were enabled.  Due to the SA 
position at 269 degrees, the effective night length of the spacecraft after 
the maneuver was 48 minutes.  Post maneuver analysis of data indicate that 
during the Yaw Around, the end-of-night load bus voltage was 25.0 volts and 
the average depths of discharge (DODs) on Batteries 2 and 3 were 
approximately 22.5 and 22.0 percent respectively.
 
UARS experienced a Solar Eclipse on 26 February 1998 in Orbit 35311 during 
battery day at approximately 057/17:07 UTC and exited at approximately 
057/17:24 UTC.  The maximum sun coverage was 86.3 percent. The WINDII 
instrument was powered on four orbits prior to the eclipse to view eclipse-
related data, and powered back off two orbits following the eclipse. ACRIM, 
SOLSTICE, and SUSIM were also powered during the eclipse.  PMON heater 
cycling was disabled during the eclipse to conserve power.  Post-eclipse 
analysis of data indicate that during the eclipse orbit, approximately 19% 
of nominal solar array input energy was lost.  During the spacecraft night 
following the eclipse, the load bus voltage reached a minimum of 23.7 
volts.  Power and thermal subsystem stability were restored within one 
orbit following the eclipse.

Spacecraft battery 1, 2, and 3 performance monitoring continues. Battery 1 
remains OFF the charge relay.  Battery 2 and Battery 3 are currently 
maintaining greater than 25.4 V end-of-night (EON) load bus voltage.  
Battery temperatures are stable with a temperature delta between Battery 2 
and Battery 3 of 1.4 degrees C.  Additional battery performance data for 
each battery on 21 February 1998 and 27 February 1998 are provided in 
Appendix D.

The clock error ranged from -0.7 to +10.7 msec during this report period.  
Clock rate adjustments are listed in Appendix C.

All instrument and subsystem engineers were advised on the initial 
excursion of ALERTS or Out-Of-Limits conditions detected by the FOT for 
this report.  A summary is listed below and the details of ALERT and Out-
Of-Limits occurrences are listed in Appendix B.

%     ALERTS            =     none
%     OUT-OF-LIMITS     =     15

The following real-time command sheets were executed for the listed 
operational element(s) during this report period (see Appendix A). 

%     FOT     03
%     HRDI    05
%     MLS     01
%     WINDII  02


UARS Anomaly Reports initiated during this report period are listed in 
Appendix E and summarized below.

%     FOT     none

TRANSPONDER FREQUENCIES:
     Transponder A:  98/041  -  2287.497104
     Transponder B:  98/042  -  2287.499330


GROUND SYSTEM OPERATION

No (0) operational support problem(s) occurred this period. Anomaly Reports 
are included in Appendix E.

The data loss calculations supplied by Data Capture Facility (DCF) from 
mission start through UTC Day 98/057 show the observatory data loss to be 
20 hours, 42 minutes, 7.540 seconds (no change since last reported).  This 
is a 0.0367 percent data loss which equals a 99.9633 percent data capture 
for the mission.

FOT is investigating the feasibility of participating in the IP Forward 
Link testing.  Due to the possible risk of the IP conversion devices 
corrupting commands, the FOT would like to test the IP link with the UARS 
Test and Training Simulator (UTTS) before transmitting any commands to the 
spacecraft.  The methodology and requirements for performing a command 
loop-back test is currently under investigation.

Testing of the latest AP software (modified to support a reduced ATC load) 
was attempted this week.  A reduced ATC memory size is required to support 
the new PMON software.  Testing failed, as a command link between MSOCC and 
the UTTS could not be established.  A second day of testing also failed due 
to the same problem.  Efforts by ATSC personnel to isolate the source of 
the problem proved unsuccessful.  Testing will resume next week.

Operational processing of level-0 telemetry analysis files continues in 
parallel on both the UMPGAL (new MPG Alpha machine) and CDHF computer 
systems.  Level-0 file transfer failures (between CDHF and UMPGAL) occurred 
on 24 February at about 02:00 UTC and on 27 February at about 19:00 UTC.  
File transfers, when they do not fail, are occurring at about 43 kbps 
effective rate.  This means a production set of level-0 files will 
typically take about 4-1/2 hours to transfer from CDHF to UMPGAL, hardly an 
acceptable transfer rate for operational products.  Until a more timely 
link for transfer of level-0 files can be established, the CDHF system will 
be considered the operational system for FOT analysis of telemetry data.


OTHER SIGNIFICANT EVENTS

Work on the upgrade of the OBC Power Monitor (PMON) software continued. The 
code is being debugged.  The PMON telemetry processing subroutine had to 
be redesigned due to excessive code usage.  The redesign of the telemetry 
processing subroutine is table-driven and very efficient.  This re-design 
could potentially be used to process all OBC telemetry from within INTER 
much more efficiently than the existing code, and all from one centralized 
piece of code.  This approach could free up tons of memory, and allow 
greater flexibility and control over OBC telemetry at the same time and, 
therefore, should be seriously considered even though an OBC reload would 
be required.

Monitoring of the magnetic field model performance continues.

FOT continues to improve a Power Profile for UARS based on the current 
status of the Modular Power System.

FOT continues to support the new UARS ground system re-engineering effort.


MEETINGS

No UARS Battery telecon was held this week.  The next telecon has not been 
scheduled.

Attended a meeting on 23 February 1998, to discuss the R&D effort to 
develop a command system for the TMOC ground system.  Collected and 
presented current commanding system documentation to Lockheed Martin and 
ICS (Interface & Control Systems) personnel.

A meeting was held with Flight Dynamics Facility (FDF) personnel on 25 
February 1998 to obtain the results of the current drag predictions 
utilizing revised solar cycle 23 predictions, revised Spacecraft weight, 
and revised Spacecraft drag area.  The new calculations predict that the 
585 -1.25 = 583.75 km lower operational limit will be reached as early as 
12 July 1998 (-2 sigma) and 03 December 1998 (+2 sigma).  The UARS Program 
Manger requested that an orbit adjust be executed by August 1998 to assure 
that skilled manpower and hardware resources are still available. The FOT 
is responsible (by 11 March 1998) for presenting an activity plan and 
timeline for accomplishing this maneuver by the planned date.  Extensive 
ground testing will be required prior to the orbit adjust, accounting for 
most of the preparation time for this maneuver.


FUTURE SIGNIFICANT EVENTS

The next UARS Yaw Around Maneuver is currently scheduled for 02 April 1998.

UARS Flight Operations plans to attend the Program Experience portion of 
the Space Power Workshop at JPL in April 1998.  UARS FOT plans on 
presenting an overview of the UARS batteries and their performance.

The UARS orbit altitude is dropping slowly and a drag makeup orbit adjust 
is targeted for 05 August 1998.


PERSONNEL CHANGES

None.


Attachments: Appendix A, Real-time Commands Sheets
             Appendix B, Out-Of-Limits & ALERT Occurrences
             Appendix C, Clock & Solar Array Rate Corrections
             Appendix D, UARS Battery Performance Data
             Appendix E, UARS Anomaly Reports



                               APPENDIX A
                       REAL-TIME COMMAND SHEETS
                      Week ending 27 February 1998

ORBIT      AOS       NO.     SUBSYS                REASON
-----      ---       ---     ------               -------  
35249   053/1344   98-061     HRDI    HTR cycle from 25 to 200 amp-min
35255   053/2329   98-062     MLS     Power OFF
35280   055/1532   98-063     HRDI    HTR Cycle from 200 to 150 amp-min
35299   056/2146   98-064   OBC/PMON  RTS-4 & RTS-70 for V/T Switch
35307   057/1027   98-065    WINDII   Power ON
35308   057/1204   98-066     HRDI    HTR cycle form 150 to 100 amp-min
35310   057/1530   98-067   OBC/PMON  NOOP  RTS 04
35313   057/2004   98-068    WINDII   Power OFF
35313   057/2004   98-069     HRDI    HTR cycle from 100 to 200 amp-min
35315   057/2334   98-070     HRDI    HTR cycle from 200 to 300 amp-min
35321   058/0622   98-071     OBC     Clk Adj fr 0.00 to 20.6 msec/day


_______________________________________________________________

                               APPENDIX B
                  OUT-OF-LIMITS & ALERTS OCCURRENCES
                      Week ending 27 February 1998

MNEMONIC      STATE         DESCRIPTION              ORBITS
---------     -----        ------------              -----
HRIFESURVTMP  Y-HI  HRDI Survival temperature   35227
HRIFESURVTMP  Y-HI  HRDI Survival temperature   35246
HRPSEQBIMON   Y-HI  HRDI Quit Bus monitor       35246,90
QTSISAIF      Y-HI  SSPP Baseplate by SISA I/F  35246,82,84,
                                                35307-315, 321-29     
WIEUTEMP      Y-LO   WINDII EU Temperature      35277-301-07,16-29
NBRECBI       Y-HI   NBTR B REC CURRENT         35308,12
WIPBVOLTAGE   Y-LO   WINDII PB VOLTAGE          35308,12
SOSTMPRNTRN   Y-LO   ENTRANCE TEMP              35312-14,21
ACTEMPANA2    Y-LO   Temp Sensor Electronics 2  35312-13
QTSSPPMX      Y-HI   SSPP -X Thermostat         35312
HRIFESURVTEMP Y-HI   IFE SURVIVAL TEMP          35312-13
HRRADTEMP     Y-HI   IFE RADIATOR TEMP          35312
HRPSEQBIMON   Y-HI   QB CURRENT MONITOR         35312
CDUNRG28      Y-LO   +28V UNREG. BUS            35312
ACTEMPANA1    Y-LO   Temp Sensor Electronics 1  35315


The following ALERT occurrences were detected:

MNEMONIC                  DESCRIPTION             ORBITS
---------                 ------------            ------
                       none this report period 
          



                               APPENDIX C
                 CLOCK & SOLAR ARRAY RATE CORRECTIONS
                      Week ending 27 February 1998

                      CLOCK DRIFT RATE ADJUSTMENTS

     ORBIT              TIME                 CLOCK RATE CHANGE
     -----              ----                 -----------------
     35321     058/06:29 (27 Feb 98)     from 00.0 to 20.6 msec/day


_______________________________________________________________

                               APPENDIX D
                    UARS BATTERY PERFORMANCE DATA
                      Week ending 27 February 1998

     21 Feb 1998 - GMT Day 052 Beta = 16.8 deg, SA Pos = 269 deg

     DIFF V (mV)     TEMP (C)   CURR (amp)   EON V   AVE C/D   AVE
BAT    MAX/MIN       MAX/MIN     MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.05/-3.99  +0.0/ +0.0   18.6     0.000    0.0
2   +33.6/ -33.6  +7.41/+5.47 +32.4/-15.2   24.8     1.023    23.1
3   +33.6/ -22.4  +5.79/+4.51 +31.6/-16.0   24.8     1.023    22.4

     27 Feb 1998 - GMT Day 058 Beta =  9.0 deg, SA Pos = 269 deg

    DIFF V (mV)     TEMP (C)    CURR (amp)   EON V   AVE C/D   AVE
BAT   MAX/MIN       MAX/MIN      MAX/MIN      MIN     RATIO   DOD(%)
---  ------------  ----------  -----------  -------  -------  ------
1  +728.0/+728.0  -3.68/-4.94  +0.0/ +0.0   18.6    0.000     0.0
2   +89.6/   0.0  +5.47/+4.19 +31.6/-13.6   25.8    1.023    21.9
3   +56.0/ -11.2  +4.19/+2.60 +30.4/-15.2   25.4    1.021    21.3


     V/T LEVEL CHANGES
ORB#     TIME          LVL FR-TO
-----  --------      ----------
      no changes



                               APPENDIX E
                         UARS ANOMALY REPORTS
                      Week ending 27 February 1998

  AR NO.   SUBSYS     ORBIT      TIME      TTR   PROBLEM/DATA LOSS
  ------   ------     -----      ----      ---   -----------------
          None this report period


      ANOMALY CLOSURE INFORMATION RECEIVED
  AR NO.   SUBSYS     ORBIT     TIME       TTR   PROBLEM/DATA LOSS
  ------   ------     -----     ----       ---   -----------------
98-001     FOT      Four     January/98  14170  Generic Late Acq.     
98-004     FOT      34874     028/1332          TAC loss. Op err.
98-005     FOT      34912     032/0147          TAC Crash.
98-006     FOT      34962     034/0949          TAC Crash.
98-008     FOT      34972     035/0156          TAC Crash



               ANOMALY INVESTIGATION REPORTS GENERATED
  AIR NO.  SUBSYS       ORBIT      TIME       TTR      PROBLEM/DATA LOSS
  -------  ------       -----      ----       ---      -----------------
          None this report period